BALLYTEIGE LITTLE, BALLYCOMMON, CO.OFFALY.
Proposed development
THE EXISTING MOBILE HOME STRUCTURE AND EXISTING FOUL WATER HOLDING TANK AND ALL ASSOCIATED EXISTING SITEWORKS AS A THREE-YEAR TEMPORARY DEVELOPMENT. PERMISSION FOR THE CONSTRUCTION OF A DOMER STYLE DWELLING WITH DETACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS
- Applicant
- Not published
- Authority
- Offaly County Council
- Decision due
- 15 Oct 2025
- Residential units
- 2
- Floor area
- 329.1 m²
Timeline
Application received
17 Apr 2025
Council asked for further information
6 Jun 2025
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
18 Aug 2025
Decision due
15 Oct 2025
Decision: conditional
14 Oct 2025
Grant issued
20 Nov 2025
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
THE EXISTING MOBILE HOME STRUCTURE AND EXISTING FOUL WATER HOLDING TANK AND ALL ASSOCIATED EXISTING SITEWORKS AS A THREE-YEAR TEMPORARY DEVELOPMENT. PERMISSION FOR THE CONSTRUCTION OF A DORMER STYLE DWELLING WITH DETACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS
THE DEMOLITION OF EXISTING BUILDINGS AND THE CONSTRUCTION OF A TWO STOREY DWELLING, A DOMESTIC GARAGE, A WASTE WATER TREATMENT SYSTEM, A NEW SITE ENTRANCE AND ALL ASSOCIATED SITE WORKS
A PERIOD OF 10 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 73.9 HECTARES, TO INCLUDE A CONTROL BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, TEMPORARY CONSTRUCTION COMPOUNDS, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO ACCESS OF THE SITE. A NATURA IMPACT ASSESSMENT (NIS) HAS BEEN SUBMITTED WITH THIS APPLICATION. THE SOLAR FARM WILL BE OPERATIONAL FOR 35 YEARS
A PERIOD OF 10 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 73.9 HECTARES, TO INCLUDE A CONTROL BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, TEMPORARY CONSTRUCTION COMPOUNDS, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO THE ACCESS OF THE SITE. A NATURA IMPACT STATEMENT (NIS) HAS BEEN SUBMITTED WITH THIS APPLICATION. THE SOLAR FARM WILL BE OPERATIONAL FOR 35-YEARS
CONSTRUCTION OF A TWO-STOREY DWELLING WITH ATTACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS
CONSTRUCTION OF A TWO-STOREY DETACHED DWELLING, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS