IN THE TOWNLANDS OF BALLYTEIGUE LITTLE AND DERRYGROGAN BIG, TULLAMORE, CO. OFFALY
Proposed development
A PERIOD OF 10 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 73.9 HECTARES, TO INCLUDE A CONTROL BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, TEMPORARY CONSTRUCTION COMPOUNDS, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO ACCESS OF THE SITE. A NATURA IMPACT ASSESSMENT (NIS) HAS BEEN SUBMITTED WITH THIS APPLICATION. THE SOLAR FARM WILL BE OPERATIONAL FOR 35 YEARS
- Applicant
- Not published
- Authority
- Offaly County Council
- Decision due
- 24 Aug 2023
Timeline
Application received
29 Jul 2022
Council asked for further information
22 Sept 2022
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
30 Jun 2023
Decision due
24 Aug 2023
Decision: conditional
24 Aug 2023
Appeal decided: conditional (ABP-318041-23)
26 Jun 2024
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
THE EXISTING MOBILE HOME STRUCTURE AND EXISTING FOUL WATER HOLDING TANK AND ALL ASSOCIATED EXISTING SITEWORKS AS A THREE-YEAR TEMPORARY DEVELOPMENT. PERMISSION FOR THE CONSTRUCTION OF A DOMER STYLE DWELLING WITH DETACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS
THE EXISTING MOBILE HOME STRUCTURE AND EXISTING FOUL WATER HOLDING TANK AND ALL ASSOCIATED EXISTING SITEWORKS AS A THREE-YEAR TEMPORARY DEVELOPMENT. PERMISSION FOR THE CONSTRUCTION OF A DORMER STYLE DWELLING WITH DETACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS
THE DEMOLITION OF EXISTING BUILDINGS AND THE CONSTRUCTION OF A TWO STOREY DWELLING, A DOMESTIC GARAGE, A WASTE WATER TREATMENT SYSTEM, A NEW SITE ENTRANCE AND ALL ASSOCIATED SITE WORKS
A PERIOD OF 10 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 73.9 HECTARES, TO INCLUDE A CONTROL BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, TEMPORARY CONSTRUCTION COMPOUNDS, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO THE ACCESS OF THE SITE. A NATURA IMPACT STATEMENT (NIS) HAS BEEN SUBMITTED WITH THIS APPLICATION. THE SOLAR FARM WILL BE OPERATIONAL FOR 35-YEARS
CONSTRUCTION OF A TWO-STOREY DWELLING WITH ATTACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS
CONSTRUCTION OF A TWO-STOREY DETACHED DWELLING, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS