Mishells, Bandon, Co. Cork, P72C448
Proposed development
Permission for change of design of works to existing dwelling to comprise construction of part single storey extension, part two-storey extension and modifications to said dwelling, as granted under permission reg. number 23/06445, and all associated site works.
- Applicant
- Not published
- Authority
- Cork County Council
- Decision due
- 13 Nov 2025
Timeline
Application received
19 Sept 2025
Decision due
13 Nov 2025
Decision: grant with conditions
12 Nov 2025
Grant issued
13 Jan 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
Permission for the construction of a dwelling house, on-site wastewater treatment system and associated siteworks. Extension of Duration to Permission granted under Planning Ref. No. 20/4481.
The provision of a Battery Energy Storage System (BESS), compound and cable route on a site of c. 4.61ha. The BESS compound will accommodate self-contained Lithium Iron Phosphate batteries within 32 no. BESS units, 8 no. MV Switchgear units, and a 38kV substation including a control room of 126m2. A cable route of c. 2km is proposed to run south from the compound to the L2033 and east along the L2033 to the nearby Bandon 110kV Substation. The proposed development includes for all associated development, site levelling, boundary treatments, security fencing, site access works, ducting and cabling and all ancillary works.
The construction of a dwelling house, on-site wastewater treatment system and associated siteworks. Extension of Duration to Permission granted under Planning Ref. No. 20/4481
Permission for works to existing dwelling to comprise construction of part single storey extension, part two-storey extension, modification to said dwelling, a detached garage, a waste water treatment system, vehicular entrance, field entrance, demolition of existing outhouse structures and all associated site works.
2km of grid connection infrastructure on the public road and agricultural land to connect the approved Finnis Solar Farm (Planning reference 17/6111) to the existing Bandon Substation and to connect two parcels of land within the consented development comprising the laying of underground electricity cables, associated infrastructure and horizontal directional drilling.
2km of grid connection infrastructure on the public road and agricultural land to connect the approved Finnis Solar Farm (Planning Reference 17/6111) to the existing Bandon Substation and to connect two parcels of land within the consented development comprising the laying of underground electricity cables, associated infrastructure and horizontal directional drilling.