Vale Road (Townland of Ballyraine Lower), Arklow, Co. Wicklow
Proposed development
Part 8 - submissions should be made to the relevant department as specified on the site notice (not to the Planning Department) - construct 2 No. social housing units and all associated works. The accommodation shall consist of the following: 1 No. 2 bed and 1 No. 3 bed single storey units
- Applicant
- Not published
- Authority
- Wicklow County Council
- Decision due
- 3 Jun 2025
Timeline
Application received
9 Apr 2025
Decision due
3 Jun 2025
Decision: unconditional
9 Jul 2025
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
the following works to connect Avoca River Park to public services: • an underground foul pump station and an above ground kiosk with a total height of 1.8m within a secure compound located on lands at Avoca River Park; • a watermain with a total length of c. 2.2km and a foul rising main with a total length of c. 2.2km from the proposed pump station, traversing lands within Avoca River Park, the existing trackway through the marsh, 10 and 11 Ferrybank and terminating in the public road (R772); • installation of fibre connections with a total length of c. 2.2km with fibre ducts; • connection to the existing Uisce Éireann foul network and watermain network; • all associated site development works above and below ground
The proposed development seeks permission to amend the development permitted under WCC Reg. Ref.: 23/72 and will consist of the following: • Reconfiguration of the internal layout of the 3-no. permitted ICT facility buildings to include ICT equipment rooms, mechanical rooms, switch rooms, electrical equipment rooms, office accommodation, storage and staff facilities at ground and first floor levels; • Amendments to the southern façade on all ICT facility buildings to include alterations to fenestration, extension of permitted louvered façade treatment, and associated alterations; • An increase of c.113 sq.m to the permitted external generator compound of each ICT facility building at ground floor to accommodate additional plant and equipment; • Amendments to plant and equipment layout at roof level and the provision of 1 no. additional roof-mounted emergency landlord generator on each ICT facility building; • Amendments to the permitted water services compound to provide for 1 no. sprinkler tank, 1 no. hydrant tank, 2 no. hydrant water tanks, 2 no. water storage tanks, 6 no. single storey pump rooms (with a gross floor area (GFA) of c. 52 sq.m each) and 1 no. single storey pump room of with a GFA of c. 46 sq.m; • Revisions to permitted site access arrangements including the omission of a permitted security hut and the provision of a revised sally port entrance system with a single storey gatehouse (c. 43 sq.m) and associated revised internal road network; • Relocation of permitted car parking spaces and the provision of 26 no. additional car parking spaces (149 no. spaces in total), Electric Vehicle (EV) car parking and ducting; • The proposed development also includes alterations to the permitted landscaping and planting, fuel filling areas, boundary treatments, security fencing, lighting, SuDS and drainage, and all associated and ancillary site development works. The operation of the development will require an EPA Industrial Emissions Directive (IE) Licence.
• 1 no. ICT facility building with a gross floor area (GFA) of c. 36,655 sq.m and a total parapet height of c.19.5m. • 2 no. ICT facilities each with a GFA of c. 4,428 sq.m and a total parapet height of c. 10.5m. • Each of the ICT facilities will accommodate ICT equipment rooms, external mechanical equipment areas, electrical equipment rooms, network rooms, ancillary office space, storage and loading bays; • The construction of a solar farm development consisting of photovoltaic (PV) panel arrays covering an area of approximately c. 2.7 ha in the east of the site, on ground mounted steel frames, underground cabling and ducting, a new gated internal track for maintenance and all associated site services works; • Relocation of the customer transformer compound permitted under WCC Reg. Ref.: 21/1080 as amended by WCC Reg. Ref.: 23/843; • The provision of process water and domestic water split tanks, process water and domestic water plantrooms, rainwater harvesting tanks, chlorine dosing kiosk, sprinkler pump rooms, sprinkler tanks, fire hydrant pump room and hydrant tank; • The provision of an internal road network and circulation areas, footpaths, 104 no. car parking spaces and 100 no. cycle parking spaces; • The construction site access arrangements and amendments to the internal road network permitted under WCC Reg. Ref.: 21/1080 as amended by WCC Reg. Ref.: 23/843; • Landscaping and planting, boundary treatments, site lighting, security fencing, all associated site works including underground foul and storm water drainage network, Sustainable Urban Drainage Systems (SuDS) measures, and utility cables, and all ancillary works. The operation of the proposed development will require an EPA Industrial Emissions Directive (IE) Licence. An Environmental Impact Assessment Report (EIAR) has been prepared
proposed development. The proposed development includes an amendment to the development permitted under Reg. Ref. 21/1080, The proposed development will consist of the following to facilitate the above. Demolition of the existing structures on the western part of the site that comprises 4 no. industrial commercial buildings, an associated hut / outbuilding, a gas enclosure, and a tank with bund wall. The removal of the remains of a previously demolished building, areas of hard standing, and existing surface treatments. The relocation of the Energy Centre 1 to the western part of the site, which will supersede the previously permitted 110kV GIS substation compound at that location under ABP Ref: VA27.309252. The proposed development will provide for a revised energy centre design, to include the provision of 8 no. gas turbines (with associated flues of 25.15m in height), 4 no. black start emergency generators and associated transformers, 2 no. single storey fuel oil pump rooms with a gross floor area (GFA) of 90.17sq.m, a single storey air compressor building with a GFA of 88.9sq.m, 4 no. fuel tanks, 2 no. MCC control rooms with a GFA of 44.17sq.m, 3 no. fire water tanks, a single storey welfare, storage, and pump room building with a combined GFA of 160.97 sq.m, a two storey MV /LV building with a GFA of 655.54sq.m, 8 no. 11kV/ 33kV step-up transformers in the north of the site, water treatment equipment, and a security hut, all within a fenced compound. The proposed development includes landscaping and planting, boundary treatments, lighting, security fencing, car parking, and all site works including underground foul and storm water drainage network (including on-site wastewater treatment system), and utility cables, along with all associated and ancillary works. An EPA- Industrial Emissions Directive (IED) licence will be applied for to facilitate the operation of the proposed development
the proposed development will consist of replacing the existing boundary fence on three of the site boundaries with a stronger more secure type of fence as shown on the drawings submitted with this application
The proposed development will consist of replacing the existing boundary fence on three of the site boundaries with a stronger more secure type of fence as shown on the drawings with this application.