Oakwood Lodge, Ballykean (Stringer), Redcross
Proposed development
Extension to rear of dwelling and velux windows to roof of dwelling and associated works
- Applicant
- Not published
- Authority
- Wicklow County Council
- Decision due
- 6 Sept 2017
Timeline
Application received
21 Apr 2017
Council asked for further information
8 Jun 2017
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
10 Aug 2017
Decision due
6 Sept 2017
Decision: conditional
31 Aug 2017
Grant issued
2 Oct 2017
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
(i) a new entrance (ii) existing entrance to be closed and made obsolete (iii) the importation of material to in-fill and re-contour the subject site, and all associated site development works. Once the importation is complete, the applicant will seed the land in line with Teagasc guidelines and return it to agricultural use. The Operational Phase will see the site being used as agricultural pastureland. The applicant proposes, subject to planning, to import clean greenfield soil and stone to remediate approximately 3.72ha. of the total site. The 3.72ha is divided into 4 distinct phases - Phase 1 is 1.82ha, Phase 2 is 0.58ha, Phase 3 is 0.66ha and Phase 4 is 0.66ha. A fill plan has been drawn up for the importation of 41,552tonnes to fill Phase 1, 25,243 tonnes to fill Phase 2, 28,596 tonnes to fill Phase 3, and 28,596tonnes to fill Phase 4, equating to a total of 123,987tonnes of soil and stone. Permission is being sought for a 5-year period and will be subject to a waste facility permit
the importation of material to in-fill and re-contour the subject site at Ballinabarny South, Redcross, Wicklow. Once the importation is complete, the applicant will seed the land in line with Teagasc guidelines and return it to agricultural use. The Operational Phase will see the site being used as agricultural pastureland. The applicant proposes, subject to planning, to import clean greenfield soil and stone to remediate approximately 3.72ha. of the total site. The 3.72ha is divided into 4 distinct phases - Phase 1 is 1.82ha, Phase 2 is 0.58ha, Phase 3 is 0.66ha and Phase 4 is 0.66ha. A fill plan has been drawn up for the importation of 41,552tonnes to fill Phase 1, 25,243tonnes to fill Phase 2, 28,596tonnes to fill Phase 3, and 28,596 to fill Phase 4, equating to a total of 123,987 tonnes of soil and stone. Permission is being sought for a 5-year period and will be subject to a waste facility permit
of extension to existing residence
the demolition of the 16sqm rear extension (total area of existing house is 64sqm), construction of a single storey render clad extension (approx. 111sqm) to the rear of the retained portion of the existing house, changes to selected window opes, external wall finishes and roof of the existing house, a bored well, a new site specific treatment unit and percolation area replacing an existing septic tank and soak pit and all associated site works