Mountneil, Carrickpheirish, Gracedieu Waterford
Proposed development
Permission for a residential development for 99no. residential units including; (a) (i) 14no. 2 storey 4 bed semi-detached units; (ii) 30no. 2 storey 3 bed semi-detached units; (iii) 12no. 2 storey 3 bed terrace units; (b) (i) 1no. 4 storey apartment block including; (ii) 1no. 1 storey creche (227m2) with ancillary rooms and external play area at ground floor; (iii) 1no. 1 storey 1 bed apartment unit at ground floor; (iv) 5no. 1 storey 2 bed apartment units at first floor; (v) 1no. 1 storey 1 bed apartment unit at first floor; (vi) 1no. 1 storey 1 bed apartment unit at second floor; (vii) 5no. 1 storey 2 bed apartment units at second floor; (viii) 5no. 1 storey 2 bed apartment units at third floor; (ix) 1no. 1 storey 1 bed apartment unit at third floor; (d) (i) 1no. 4 storey apartment block including; (ii) 4no. 1 storey 2 bed apartment units at ground floor; (iii) 2no. 1 storey 1 bed apartment unit at ground floor; (iv) 5no. 1 storey 2 bed apartment units at first floor; (v) 1no. 1 storey 1 bed apartment unit at first floor; (vi) 1no. 1 storey 1 bed apartment unit at second floor; (vii) 5no. 1 storey 2 bed apartment units at second floor; (viii) 1no. 1 storey 1 bed apartment unit at third floor; (ix) 5no. 1 storey 2 bed apartment units at third floor; (e) (i) 2 no. external communal bin store (64.2m2); (ii) 2 no. external bike store (18.5m2); (iii) 1no. external apartment storage (29.4m2); (f) all associated site works including (i) foul and surface water drainage, and water mains; (ii) SuDS measures; (iii) vehicular road and pedestrian links to existing Mountneil housing estate; (iv) car parking; (v) landscaping and public lighting; (vi) 2no. ESB Kiosks and (vi) all other associated site development works
- Applicant
- Not published
- Authority
- Waterford City and County Council
- Decision due
- 24 Aug 2026
- Residential units
- 56
- Floor area
- 7000 m²
Timeline
Application received
19 Dec 2025
Council asked for further information
19 Feb 2026
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
15 Jul 2026
Decision due
24 Aug 2026
Decision: conditional
20 Aug 2026
Grant issued
28 Sept 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
Proposed single storey plant room extension to the main facility and to include all associated site works, drainage, alterations to existing site levels and ancillary site development works to accommodate the above works, all at their premises
Proposed single storey plant room extension to the main facility and to include all associated site works, drainage, alterations to existing site levels and ancillary site development works to accommodate the above works, all at the premises
The development of 3 no. new backup generators and support structure (located to the north side of the site) and associated adjacent single storey foam house (7m² ) and to include all associated site works, drainage, alterations to existing site levels and ancillary site development works to accommodate the above works, all at their site.
Proposed single storey cold room extension and single storey electrical switch room extension to the north of the site and to include all associated site works, drainage, alterations to existing site levels and ancillary site development works to accommodate the above works
Proposed new pedestrian entrance adjacent to the existing South vehicular entrance to include all associated paths, piers, walls, fencing, gates, site works, drainage, alterations to existing site levels and ancillary site development works to accommodate the above works, all at their premises at IDA Industrial Park, Old Kilmeaden Road, Knockhouse Lower, Waterford.