1 Canopy Street, Cashel, Co. Tipperary
Proposed development
A change of use of part of the first floor of the property, from private residential to an Airbnb including all associated site development works
- Applicant
- Not published
- Authority
- Tipperary County Council
- Decision due
- 2 Jun 2026
Timeline
Application received
8 Apr 2026
Decision due
2 Jun 2026
Decision: conditional
28 May 2026
Grant issued
1 Jul 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Similar applications refused nearby
Since 2019 the council has refused these applications for the same kind of development (change of use) within 300 m, and they weren't overturned on appeal. They're useful planning history for your letter, and we'll suggest them when you object.
Planning history within 750 m
the removal/deconstruction of an external bar and canopy structure to the rear yard, and RETENTION PERMISSION for 1) combining two public houses into one public house, and 2) constructing toilet facilities associated with public house, including all associated site development works
1) a domestic extension to the rear of the dwelling, 2) the construction of the roof of the dwelling to a lower ridge height than that originally permitted, 3) elevational amendments, and including all associated site development works
1) domestic extension to the rear of the dwelling, 2) the raising of a portion of the roof to the rear of the dwelling, 3) a boiler house, 4) a fuel shelter, 5, the removal of the roadside boundary wall and the construction of a roadside railing and gate, and including all associated site development works
the construction of a four-storey extension to the existing Cashel Palace Hotel comprising 29 no. additional guestrooms, front of house reception area, meeting/conference rooms, gym, hair salon, juice bar, rooftop restaurant and bar area, together with ancillary staff and back of house uses including administration office, kitchen, plant/comms areas and storerooms. The proposed extension will link to the main hotel via the existing Spa Building with the construction of a glazed link corridor positioned at first floor level within the proposed extension. Internal works are also proposed within the existing Spa Building to facilitate this including demolition works to facilitate construction of the glazed link and the construction of an access stairs, and internal demolition works to facilitate reconfiguration of the Spa reception area and internal access arrangement. The development also includes upgrades to the Main Street / Buckley Carpark to provide a new link street, upgrades to the existing carpark including revised carparking layout, and the construction of a new surface carpark to provide additional private carparking spaces to serve the hotel within the rear garden of the AIB Bank, no. 66 Main Street, Cashel, Co. Tipperary to be facilitated by the partial demolition of the party wall separating the AIB curtilage from the existing public carpark and creation of a controlled (barriered) vehicular entrance. Landscaping and public realm upgrades, site services including drainage infrastructure, and all associated ancillary development works are also proposed. Part of the site is located within the Cashel Town Architectural Conservation Area. The works will be carried out within the curtilage of the following 5 structures on the Record of Protected Structures of the Cashel and Environs Development Plan 2009-2015: RPS Ref. 7 (Cashel Town Walls); RPS Ref. 8 (Cashel Palace Hotel); RPS Ref. 80 (Palace School House), RPS Ref. 81 (Cashel Palace Gate Lodge) and RPS Ref. 30 (No. 66 Main Street). No direct works are proposed to many of the listed protected structures with the exception of RPS30
the filling of existing land depression /quarry and to reinstate ground with inert material to original levels, subject to approval of an Article 57 licence & to also include all associated site development works for a temporary haul path & alteration of existing entrance
fill the existing land depression /quarry and reinstate ground with inert material to original levels including all associated site development works