Powerstown Demesne and Burgagery Lands-East, Clonmel, Co. Tipperary
Proposed development
REDIII 10-year planning permission for a solar energy development with a total site area of 15.9 hectares comprising (i) photovoltaic solar panels on mounting frames; (ii) electrical transformer stations; (iii) underground electrical and communications cabling; (iv) upgraded and new on-site access tracks; (v) security fencing and gates; (vi) pole-mounted security cameras; and (vii) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. The planning application is accompanied by an Appropriate Assessment Screening Report.
- Applicant
- Not published
- Authority
- Tipperary County Council
- Decision due
- Not available
Timeline
Application received
19 Nov 2025
Decision due
Not available
Site location with nearby applications
Can't object to this one
The council has marked this application invalid or closed.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
RED III, A 10-year planning permission for a solar energy development with a total site area of 15.9 hectares comprising (i) photovoltaic solar panels on mounting frames; (ii) electrical transformer stations; (iii) underground electrical and communications cabling; (iv) upgraded and new on-site access tracks; (v) security fencing and gates; (vi) pole-mounted security cameras; and (vii) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. The planning application is accompanied by an Appropriate Assessment Screening Report
a 10-year planning permission for a solar energy development with a total site area of 15.9 hectares comprising (i) photovoltaic solar panels on mounting frames; (ii) electrical transformer stations; (iii) underground electrical and communications cabling; (iv) upgraded and new on-site access tracks; (v) security fencing and gates; (vi) pole-mounted security cameras; and (vii) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. The planning application is accompanied by an Appropriate Assessment Screening Report
RED III application for a 10-year planning permission for a solar energy development with a total site area of 15.9 hectares comprising (i) photovoltaic solar panels on mounting frames; (ii) electrical transformer stations; (iii) underground electrical and communications cabling; (iv) upgraded and new on-site access tracks; (v) security fencing and gates; (vi) pole-mounted security cameras; and (vii) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. The planning application is accompanied by an Appropriate Assessment Screening report
the construction of two above ground water reservoirs, a new well, and all associated site development works
the construction of a (i) calf shed, (ii) slatted tank, (iii) manure slab with wall and all associated site works
the alterations to previously granted permission (PD. Ref: 2460001), for increase in height of 2.5m to warehouse building as granted, together with all associated site development works