AbbVie Ireland NL B.V., Manorhamilton Rd Barroe, Co Sligo.
Proposed development
The construction of a new single-story extension to the south of the existing B-40 building with associated of the existing facility, with a floor area of circa 114 sq metres, with an overall height of 6.5 metres, and all associated site services.
- Applicant
- Not published
- Authority
- Sligo County Council
- Decision due
- 14 Dec 2026
Timeline
Application received
20 Oct 2026
Last day for public submissions (est.)
Mon 23 Nov 2026
Decision due
14 Dec 2026
Site location with nearby applications
Affected by this development?
Anyone can make a submission. It takes about 10 minutes, the council must consider it, and it preserves your right of appeal. The council charges €20 per submission.
Tell your neighbours
Each household's own submission counts. Share this application so neighbours can object before the deadline.
Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
The development will consist of the conversion of temporary contractor car parking area to permanent car parking area with additional car parking (67 no. spaces including 4 no. new disabled accessible parking spaces and 16 new EV charging spaces), within the existing site including all associated site works and services.
Permission for 1) The construction of a 6.1m high single storey extension with a floor area of 176m2 for the Pack-Off area located at the southeast corner of the existing production facility, 2) The construction of a 14m high new fire escape staircase of 55.4m2 connecting the ground floor, mezzanine and roof located at the southeast corner of the existing warehouse, 3) External galvanised steel fire escape stairs to south elevation of existing warehouse to provide fire escape from new Pack-Off roof and existing mezzanine to ground floor level
Replacement of 3no. signs and all associated site development works. Sign 1 (4.2m x 0.4m) is a low-level wall mounted illuminated sign at the left hand side of the main entrance. Sign 2 (4.2m x 0.4m) is a low-level wall mounted illuminated sign at the right hand side of the site entrance. Sign 3 (1.4m x 3.5m) is non illuminated triangle totem sign at the main site entrance at
1) The construction of a 6.1m high single storey extension with a floor area of 176m2 for the Pack-Off area located at the southeast corner of the existing production facility; 2) The construction of a 14m high new fire escape staircase of 55.4m2 connecting the ground floor, mezzanine and roof located at the southeast corner of the existing warehouse at Abbvie Ballytivnan facility; and 3) External galvanised steel fire escape stairs to south elevation of existing warehouse to provide fire escape from new Pack-Off roof and existing mezzanine to ground floor level.
for development consisting of the installation of 2 no. 1.65MVA emergency back-up Hydrotreated Vegetable Oil (HVO) generators measuring 6.26m in length, 2.66m in width and 3.39m in height connected to an existing MV switchroom located on existing concrete plinths with associated 1 no. 45,000 litre Fuel Storage Tank located on existing concrete plinth all enclosed in existing security palisade fencing and all ancillary site works with access taken from 3 no. existing access gates
Installation of ground-mounted solar photovoltaic (PV) panels on lands of 2.88 hectares; Transformer station and five inverters; Access track; New access gate; Perimeter fencing; Placement of underground cabling; Landscaping enhancements; CCTV; and all associated ancillary development, site works and services. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development and will be submitted to the planning authority with the application.