ObjectRight
Back to search
2560036Grantedpermission

Townland of Ballysumaghan, Srananagh, Co. Sligo

Not open for objections: The council has already decided this application.

Proposed development

The development will consist of an enclosed battery energy storage system compound on c. 2.04 hectares. The development will consist of up to 15 no. BESS units comprising of battery cells, modules and racks set within containers stored on concrete bases and ancillary equipment (4 no. BESS containers within each ‘BESS unit’); an individual unit inverter at each BESS unit with some additional ancillary equipment; a Transformer Compound, Control building (including control room and switch room), Interface Kiosk and all associated electrical infrastructure equipment and works; attenuation drainage pond to the northwest of the site; a temporary site compound and all associated works (to be located to the south of the BESS site); a new vehicular entrance to local road and all associated internal access tracks; associated electrical underground cabling and ducting works facilitating the connection of proposed electrical substation to the adjacent Srananagh transmission station; all associated site development, lighting, landscaping, CCTV, security fencing, boundary treatment works above and below ground and all associated ancillary infrastructure.

Applicant
Not published
Authority
Sligo County Council
Decision due
12 Oct 2025
Official file, drawings & documents on the council portal

Timeline

  1. Application received

    5 Feb 2025

  2. Council asked for further information

    31 Mar 2025

  3. Further information received. If the council treats it as significant, a new submission period opens (check the council's file)

    15 Sept 2025

  4. Decision due

    12 Oct 2025

  5. Decision: conditional

    3 Oct 2025

  6. Grant issued

    5 Nov 2025

Loading map…

Site location with nearby applications

Can't object to this one

The council has already decided this application.

See applications open for objections →

Keep an eye on this area

We'll email you when new applications are lodged nearby.

Planning history within 750 m

2560170Granted

the development will consist of amendments to the permitted but not yet constructed Synchronous Compensator grid stabilisation facility granted under Planning Ref: PL22/352 (Parent Permission). The proposed amendments comprise: a) exclusion of the consented 220kv high voltage gas insulated switchgear (GIS) building and associated compound; and b) a reconfigured and extended high inertia synchronous compensator (HISC) compound containing the consented 1 no. HISC unit enclosed within a steel clad framed style structure (12.1m max height) and all previously consented supporting plant and equipment, additional HV electrical plant and equipment, and all associated and ancillary site works necessary to facilitate the development including: all necessary drainage systems, foundations works, various underground cables and ducts, equipment plinths, internal services roads, rainwater harvesting systems, welfare and office units, material storage containers, compound lighting and palisade gates and fencing, security lighting, CCTV, hardstanding areas and boundary security fence. The remaining elements of the development permitted under Parent Permission Planning Ref: PL22/352 remain unchanged - DEV CONTRIBUTIONS PAID BUT NO COMMEMENCEMENT NOTICE SUBMITTED ON THE BCMS 11/12/2025

Ballysumaghan, Sooey, Co. Sligo Sligo County Council Received 2 May 2025
2460413Granted

to (a) retain rear extension to existing dwelling house (b) elevation changes to existing dwelling house (c) revision of site boundaries to that previously granted planning permission under reference number PL 21/375 (d) retain revised location of effluent treatment unit to that previously granted under reference number PL 21/375 together with all ancillary site works and services on site

Ballysumaghan, Ballintogher, Co. Sligo Sligo County Council Received 15 Nov 2024
2360214Granted

A 10 year planning permission for the construction of a: 1. enclosed battery energy storage system compound on a total of up to c. 5.05 hectare site, to include: • 150 battery units set inside storage blocks on concrete support structures containing Heating, ventilation and air conditioning unit (HVAC units); • Transformer and inverter units on concrete support structures; • 1 no. two storey customer 220kV Gas Insulated Substation (GIS) (See Drawing 23553-201 and 23552-202); • 1No. Customer Control Building and 220kV Transformer with associated Switchgear; • 3No. Containing Back-up Generators, Auxiliary Transformers, Switchgear containers, LV and Control Containers; • 1No. Lightning Pole; • 2No. Firewater reservoir ponds with Pumping station and 1No. detention basin with associated drainage systems (as per Drawing 23553-102); • Security gates, 2.6m palisade perimeter security fencing, CCTV and lighting system, landscaping works and all associated ancillary infrastructure; • 4.5m wide Access tracks and site entrance along with upgrade works on the public site access road (c.950m), • Associated electrical cabling and ducting and all other ancillary and miscellaneous site works including site clearance; site access, internal roads and development of areas of hard standing including a maintenance lay-down area. • c.100m of underground cabling ducts and cable to the neighbouring ESB substation. A Natura Impact Statement has been prepared for this proposed development to assess and mitigate any potential ecological impacts. the development will be located at a site in the townland of Ballysumaghan, Fannybrook, Quarry Lane Co. Sligo. The proposed development will have a projected life span of 35 years.

Townland of Ballysumaghan Fannybrook, Quarry Lane Co. Sligo, Ireland Sligo County Council Received 17 Aug 2023
22369Withdrawn

development consisting of the development of a battery energy storage system. The development will consist of a 10 year planning permission for the construction of a: (1) enclosed battery energy storage system compound on a total of up to c. 1.7 hectare site, to include: 1 no. single storey customer substation and 1 no. TSO substation (c. 182m2), control and switch rooms, up to 174 battery units set inside storage blocks on concrete support structures including heating, ventilation and air conditioning unit (HVAC units), transformer and inverter units. Including access tracks and site entrance along with upgrade works on the public roads (c.800m), associated electrical cabling and ducting, security gates, palisade perimeter security fencing (c. 2.6m height), CCTV system, landscaping works and all associated ancillary infrastructure. The total development area including the area of public road improvements is c.2.3 hectares. A Natura Impact Statement has been prepared for this proposed development to assess and mitigate any potential ecological impacts

Townland of Ballysumaghan, Fannybrook, Quarry Lane Sligo County Council Received 9 Nov 2022
22352Granted

development consisting of (a) A High Inertia Synchronous Compensator (HISC) compound containing 1 No. HISC unit enclosed within a steel clad framed style structure (12.1m max height) and supported by 7 No. electrical equipment containers (containing ancillary power supply products including static frequency converters, MV switchgear, exciters, LV distribution, control room); 4 No. external cooler units; main, auxiliary & start-up electrical transformers, generator circuit breakers, switchgear equipment, and 1 No. back up diesel generator and associated diesel storage tank; (b) A 220kV High Voltage Gas Insulated Switchgear (GIS) compound containing a GIS building with all control & HV equipment within a single storey building (13.2m max height). The building will be surrounded by a compound road and contained within a 2.6 high galvanised steel palisade fence; (c) A 220kV underground cable to the existing adjoining Eirgrid substation boundary; (d) New access road and entrance from the L5204; (e) All associated and ancillary site works necessary to facilitate the development including: all necessary drainage systems, foundations works for the above compounds, various underground cables and ducts, equipment plinths, internal services roads, rainwater harvesting systems, welfare and office units, 2 No. material storage containers, compound lighting and palisade gates and fencing, security lighting, CCTV, hardstanding areas and boundary security fence. Planning permission to construct the development is sought for a period for 10 years. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development and accompanies the application.

Ballysumaghan, Sooey, County Sligo Sligo County Council Received 27 Oct 2022
22351Granted

development consisting of: The 10 year permission for the construction and operation of a synchronous condenser facility. The facility will be a fenced compound ca. 1.196ha in size. The development will have a 30 year operational lifetime and will consist of a synchronous condenser, which will include the following elements: generator and flywheel building (ca. 600 sq.m., ca. 12.5m high) to house the equipment including the generator, flywheel, lube oil skid, vacumn skid, TEWAC pump skid, reverse switch cubicle and star point cubicle; SFC start-up equipment room (ca. 43.650 sq.m., ca. 4.20m high); AC/DC room (ca. 81.480 sq.m., ca. 4.20m high); C&P room (ca. 70.685 sq.m., ca. 4.20m high); battery room (ca. 28.130 sq.m., ca. 4.20m high); storage room (ca. 49.200 sq.m., ca. 4.20m high); supporting components of plant within the compound that include: outdoor cooler (ca. 190.925 sq.m., ca. 2.660m high); start-up transformer & auxiliary transformer structure (ca. 68.265 sq.m., ca. 4.50m high; step-up transformer (ca. 170.985 sq.m., ca. 8.0m high) partially surrounded by a fire wall; and, generator circuit breaker (40.160 sq.m., ca.10m high). All other ancillary and miscellaneous site works including: six (6 No.) lightening masts - height of lightening masts will be determined by lightening protection study prior to commencement of construction; site clearance; site access; separation walls (ca. 8m high) to the south of the transformers; internal hardcore access track; and, development of areas of hard standing including a maintenance layout area. The development will be bound by 2.4m high perimeter fencing. The application is accompanied by a Natura Impact Statement (NIS)

Ballysumaghan, Co. Sligo Sligo County Council Received 26 Oct 2022