Proposed development

A) The erection of a temporary 100m high lattice type meteorological mast which will be secured to ground anchors by stay wires and will include instruments for measuring local climate conditions, services, and associated equipment; b) A fixed red aviation light will be fitted near the top of the lattice section of the proposed meteorological mast; c) Bird flight deterrent markers fitted to each stay wire at approximately 10m intervals; and d) All associated ancillary works. The temporary meteorological mast development will remain in position for a period of 5 years after which the mast, instruments, services, equipment, and all associated ancillary works will be removed. The purpose of the meteorological mast is to accurately measure the weather conditions at this site

Applicant
Not published
Authority
Offaly County Council
Decision due
20 Jan 2026
Official file, drawings & documents on the council portal

Timeline

  1. Application received

    17 Nov 2025

  2. Decision due

    20 Jan 2026

  3. Decision: conditional

    20 Jan 2026

  4. Grant issued

    23 Feb 2026

Loading map…

Site location with nearby applications

Can't object to this one

The council has already decided this application.

See applications open for objections →

Keep an eye on this area

We'll email you when new applications are lodged nearby.

Planning history within 750 m

2560542Awaiting decision

the development at this site located in the townland Clonarrow or Riverlyons, Co. Offaly.The Development will consist of: a) The erection of a temporary 100m high lattice type meteorological mast which will be secured to ground anchors by stay wires and will include instruments for measuring local climate conditions, services, and associated equipment; b) A fixed red aviation light will be fitted near the top of the lattice section of the proposed meteorological mast; c) Bird flight deterrent markers fitted to each stay wire at approximately 10m intervals; and d) All associated ancillary works. The temporary meteorological mast development will remain in position for a period of 5 years after which the mast, instruments, services, equipment, and all associated ancillary works will be removed. The purpose of the meteorological mast is to accurately measure the weather conditions at this site

Clonarrow, or Riverlyons, County Offaly Offaly County Council Received 7 Nov 2025
2560189Granted

for the erection of 4 wind turbines. A 10-year planning permission and 35 year operational life from the date of commissioning of the entire wind farm is being sought. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS). See full Development Description in attached document '7048 CWF - Development Description'.

Clonarrow or Riverlyons, and Killoneen, Co. Offaly. Offaly County Council Received 23 May 2025
2560151Awaiting decision

the dev.will incl.the following main components:•Erection of 4wind turbines;The candidate wind turbines for T1, T2 and T4 have a rotor diameter of 150m, a hub height of 105m and a tip height of 180m. The candidate wind turbine for T3 has a rotor diameter of 117m,a hub height of 91.5m & a tip height of 150m;•Construction of permanent Turbine Hardstands & Turbine Foundations;•Construction of new permanent internal Access Tracks & upgrade of existing internal Access Tracks;•Development of an internal site drainage network & sediment control systems;•Construction of a permanent 38kV Onsite Substation with surrounding palisade fence 2.6m in height;•Installation of battery arrays located within container units (4 no. units) and associated electrical plant for grid stabilisation adjacent to Onsite Substation building with surrounding palisade fence 2.6m in height;•All associated internal underground electrical &communications cabling connecting the wind turbines to the Onsite Substation;•All associated site development works including soil excavation, spoil storage & biodiversity enhancement measures;•Installation of a meteorological mast (32m in height) for monitoring wind speeds, set in a 5m x 5m reinforced concrete foundation with surrounding paladin fence 2.4m in height;•Installation of a Relay Mast (to re-route the Three Ireland radio link between Mount Lucas and Curragh) 19.8m in height including lightning protection rods set in an 8m x 8m reinforced concrete foundation with surrounding paladin fence 2.4m in height with an adjacent outdoor cabinet on a 3m x 2m concrete base;•Temporary Road widening and strengthening works at the R402 and L50203 junction to accommodate abnormal load deliveries;•Existing bridge on L50203 (ITM 650044E, 727144N) to be permanently upgraded to accommodate abnormal load deliveries;•Temporary bridge & temporary local access road to facilitate local traffic while the bridge upgrade works are being carried out;•Upgrade of an existing Site entrance located on a private road off the L50203; and•Construction of a Temporary Construction Compound with associated temporary site offices, parking areas, security fencing welfare facilities & wastewater holding tank. An additional Temporary Construction Compound will be constructed for the bridge upgrade & temporary bridge works. A 10 year planning permission & 35year operational life from the date of commissioning of the entire wind farm is being sought. EIAR & NIS accompany this application