2460175Awaiting decisionpermission

Tullamore Distillery Campus at Ballard & Clonminch, Tullamore, Co. Offaly

Not open for objections: The council has marked this application invalid or closed.

Proposed development

The construction of a solar PV development with an installed capacity of up to 2.6 MWdc (MEC=0) to provide electrical power to the existing distillery comprising approximately 4,100 no. photovoltaic panels on ground mounted frames within a site area of 3.90 hectares and associated ancillary development including 1 no. transformer station, 5 no. CCTV security cameras mounted on 8 metre high poles, perimeter security fencing (2.4 metres high), internal access tracks, extension to existing maintenance access track on the site to the solar PV development, installation of underground cable to connect the transformer station and the distillery and site works required to facilitate the development including the provision of a secondary vehicle access and gate on the northern boundary of the site. The proposed development is for modifications to an establishment to which the major accidents directive applies and is for the purposes of an activity requiring an integrated pollution prevention and control licence

Applicant
Not published
Authority
Offaly County Council
Decision due
Not available
Official file, drawings & documents on the council portal

Timeline

  1. Application received

    20 May 2024

  2. Decision due

    Not available

Loading map…

Site location with nearby applications

Can't object to this one

The council has marked this application invalid or closed.

See applications open for objections →

Keep an eye on this area

We'll email you when new applications are lodged nearby.

Planning history within 750 m

2460529Granted

the construction of a 12.8m x 4.6m x 4.5m high forklift charging station (58.88 sqm) on an existing concrete yard slab. The proposed development is for modifications to an establishment to which the major accidents directive applies and is for the purposes of an activity requiring an integrated pollution prevention and control licence.

Tullamore Distillery Campus at Ballard & Clonminch, Tullamore, Co. Offaly Offaly County Council Received 23 Dec 2024
2460250Granted

the construction of a solar PV development with an installed capacity of up to 2.6 MWdc (MEC=0) to provide electrical power to the existing distillery comprising approximately 4,100 no. photovoltaic panels on ground mounted frames within a site area of 3.90 hectares and associated ancillary development including 1 no. transformer station, 5 no. CCTV security cameras mounted on 8 metre high poles, perimeter security fencing (2.4 metres high), internal access tracks, extension to existing maintenance access track on the site to the solar PV development, installation of underground cable to connect the transformer station and the distillery and site works required to facilitate the development including the provision of a secondary vehicle access and gate on the northern boundary of the site. The proposed development is for modifications to an establishment to which the major accidents directive applies and is for the purposes of an activity requiring an integrated pollution prevention and control licence

Tullamore Distillery Campus Ballard & Clonminch, Tullamore, Co. Offaly Offaly County Council Received 3 Jul 2024
2460248Granted on appeal

Retention of dwelling house with revised site layout, house previously granted under 17/258 and EX/22012 incorporating altered position of house on site and permission to complete dwelling house, and all associated site works.

Clonminch, Tullamore, Co Offaly Offaly County Council Received 2 Jul 2024
2460199Awaiting decision

the construction of a solar PV development with an installed capacity of up to 2.6 MWdc (MEC=0) to provide electrical power to the existing distillery comprising approximately 4,100 no. photovoltaic panels on ground mounted frames within a site area of 3.90 hectares and associated ancillary development including 1 no. transformer station, 5 no. CCTV security cameras mounted on 8 metre high poles, perimeter security fencing (2.4 metres high), internal access tracks, extension to existing maintenance access track on the site to the solar PV development, installation of underground cable to connect the transformer station and the distillery and site works required to facilitate the development including the provision of a secondary vehicle access and gate on the northern boundary of the site. The proposed development is for modifications to an establishment to which the major accidents directive applies and is for the purposes of an activity requiring an integrated pollution prevention and control licence

Tullamore Distillery Campus at Ballard & Clonminch, Tullamore, Co. Offaly Offaly County Council Received 31 May 2024
23266Granted on appeal

ON THE GRANT OF OUTLINE PERMISSION REF. NO. PL2/20/326 FOR THE DEVELOPMENT OF TWO NO. TWO STOREY HOUSES, ALL ANCILLARY SERVICES AND WORKS

CLONMINCH LANE, CLONMINCH, TULLAMORE CO. OFFALY Offaly County Council Received 8 Jun 2023
22281Granted

THE REPLACEMENT OF THE EXISTING 16M HIGH WOOD POLE WITH A PROPOSED 24 METRE HIGH LATTICE TELECOMMUNICATIONS STRUCTURE WITH ANTENNAE, DISHES AND ASSOCIATED EQUIPMENT AND GROUNDWORKS. ACCESS VIA EXISTING SUBSTATION ENTRANCE

ESB TELECOM'S COMPOUND AT ESB'S CLONMINCH 38KV SUBSTATION, CLONMINCH LANE TOWNLAND OF CLONMINCH, TULLAMORE CO. OFFALY Offaly County Council Received 2 Jun 2022