Loughlinstown, Ratoath, Co.Meath
Proposed development
THE DEVELOPMENT WILL CONSIST OF A DWELLING AND GARAGE WITH A SUITABLE WASTEWATER TREATMENT UNIT AND ASSOCIATED SITE WORKS. SIGNFICANT FURTHER INFORMATION/REVISED PLANS SUBMITTED ON THIS APPLICATION
- Applicant
- Not published
- Authority
- Meath County Council
- Decision due
- 21 Jul 2026
- Residential units
- 1
- Floor area
- 268 m²
Timeline
Application received
27 Mar 2026
Council asked for further information
21 May 2026
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
16 Jun 2026
Decision due
21 Jul 2026
Decision: conditional
21 Jul 2026
Grant issued
27 Aug 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
RED III - Construction of a solar PV energy development associated Battery Energy Storage System (BESS) facility with an operational life of 40 years on lands totalling approximately 36.3 hectares. The development will consist of the installation of approximately 208,600 sq. m. of photovoltaic panels on ground mounted frames and associated ancillary development including 3 no. transformer stations, string-inverters attached to panel frames, 25 no. CCTV security cameras mounted on 4 metre high poles, deer-proof perimeter security fencing (2 metres high) raised 200mm to allow for the movement of small mammals and gates; a BESS facility comprising an electrical compound, 180 no. battery storage units, electrical transformer/inverter station modules, 45 no. transformers, 3 no. storage containers, 3 no. 33 kV switch gear rooms, 1 no. control room building, 1 no. water tank, 1 no. underground fire water containment tank, a surface water infiltration area and 7 no. CCTV cameras enclosed with 2.5 metre high security fencing; the creation of a new access on L50161 public road to facilitate construction and operational phase access; internal access tracks between the solar arrays and the site entrance; a temporary construction compound; and all ancillary development works including landscaping and underground cable to connect the proposed transformer stations to a proposed 110kv substation with electrical control building and associated compound the subject of a separate planning permission under the Planning and Development (Strategic Infrastructure) Act 2006. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application
the development will consist of the construction of a garage, 4 number stables, manure pit and all associated works
permission to (a) demolish existing rear extension, (b) construct a single storey extension to the rear, & (c) front porch all associated site with internal modifications & all associated site development works
the development will consist of minor alterations to previously approved planning 211335, consisting of the omission of the first floor and minor adjustments to the ground floor
(a) 2 no. water treatment balance tanks (capacity 1200 m3 each) and new pump station on new concrete base, (b) new overground and part underground flow and return pipework from existing water treatment plant to new water treatment balance tanks, (c) new compacted hardcore access roadway and (d) all associated site works
the provision of a dwelling and garage with wastewater treatment system and associated site works