Liscartan and Knockumber, Navan, County Meath
Proposed development
A ten-year planning permission for a solar energy development with a total site area of approximately 34 hectares comprising (i) photovoltaic solar panels on steel mounting frames; (ii) electrical inverters; (iii) electrical power stations; (iv) an electrical control building and associated electrical apparatus; (v) underground electrical and communications cabling; (vi) on-site access tracks; (vii) a temporary construction compound; (viii) security fencing and security gates; (ix) pole-mounted security cameras; and (x) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. This development is related to an activity requiring an Industrial Emissions Licence. This planning application is accompanied by an Environmental Impact Assessment Screening Report and a Natura Impact Statement
- Applicant
- Not published
- Authority
- Meath County Council
- Decision due
- 18 Apr 2024
Timeline
Application received
23 Feb 2024
Decision due
18 Apr 2024
Decision: conditional
16 Apr 2024
Grant issued
28 May 2024
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
planning application for permission for the construction of a single storey detached dwelling including wastewater treatment system and percolation area, new entrance onto public road and all associated site works
construction of proposed commercial storage unit, installation of proposed wastewater treatment system and percolation area, including all ancillary site works
retention permission of an existing prefab unit to be used as accommodation for the keeping of dogs as a boarding facility and permission for associated entrance gate signage
retention permission of an existing prefab unit to be used as accommodation for the keeping of dogs as a boarding facility and permission for associated entrance gate signage
a ten-year planning permission for a solar energy development with a total site area of approximately 34 hectares comprising (i) photovoltaic solar panels on steel mounting frames; (ii) electrical inverters; (iii) electrical power stations; (iv) an electrical control building and associated electrical apparatus; (v) underground electrical and communications cabling; (vi) on-site access tracks; (vii) a temporary construction compound; (viii) security fencing and security gates; (ix) pole-mounted security cameras; and (x) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. This development is related to an activity requiring an Industrial Emissions Licence. This planning application is accompanied by an Environmental Impact Assessment Screening Report and a Natura Impact Statement
the relocation and enlarging of domestic garage previously granted planning permission under NA/202019