The proposed development which will consist of the following elements: the installation and operation of 1no. battery energy storage system compound containing battery energy storage containers, 1no. electrical substation and compound, connected to the national grid system via c. 50m of underground cable to the ESB Castlebar 38kV substation, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road, associated ancillary site development, landscaping and reinstatement works. The operational lifespan of the development will be 35 years. The site of the proposed development has a total area of 0.89 hectares.

Applicant
Not published
Authority
Mayo County Council
Decision due
15 Mar 2026
Official file, drawings & documents on the council portal

Timeline

  1. Application received

    17 Nov 2025

  2. Council asked for further information

    15 Jan 2026

  3. Further information received. If the council treats it as significant, a new submission period opens (check the council's file)

    16 Feb 2026

  4. Decision due

    15 Mar 2026

  5. Decision: conditional

    12 Mar 2026

  6. Grant issued

    13 Apr 2026

Loading map…

Site location with nearby applications

Can't object to this one

The council has already decided this application.

See applications open for objections →

Keep an eye on this area

We'll email you when new applications are lodged nearby.

Planning history within 750 m

2660503Awaiting decision

Planning Permission to construct a dwelling house and garage and connect into the existing public services together with all associated site works

Mountgregory, Castlebar, Co. Mayo Mayo County Council Received 26 Jun 2026
2560804Awaiting decision

The proposed development which will consist of the following elements: the installation and operation of 1no. battery energy storage system compound containing battery energy storage containers, 1no. electrical substation and compound, connected to the national grid system via c. 50m of underground cable to the ESB Castlebar 38kV substation, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road, associated ancillary site development, landscaping and reinstatement works. The operational lifespan of the development will be 35 years. The site of the proposed development has a total area of 0.89 hectares.

Aghalusky, Castlebar, Mayo Mayo County Council Received 11 Nov 2025
2560290Withdrawn

The development will consist of the construction of a private dwelling house, domestic garage and effluent treatment system together with all ancillary site works.

Liscromwell, Castlebar, Co. Mayo Mayo County Council Received 12 May 2025
2460383Granted

The development will consist of the construction of a new dwelling house, garage, on-site wastewater treatment system, and connection to existing services together with all ancillary site development works.

Liscromwell, Castlebar, Co. Mayo Mayo County Council Received 21 Jun 2024
22755Granted

CONSTRUCTION OF A DWELLING HOUSE AND DOMESTIC GARAGE,CONNECTION TO EXISTING PUBLIC SERVICES, TOGETHER WITH ANCILLARY SITE WORKS

DRUMASK, CASTLEBAR Mayo County Council Received 5 Sept 2022
22596Granted

The development consists of the retention of a converted domestic garage granted under P98/1485 to habitable space, and the retention of the converted attic space over the original domestic garage for domestic use, including the dormer window installation

Aghalusky, Castlebar, Co. Mayo Mayo County Council Received 21 Jul 2022