34 Sheelin Rd, Caherdavin Park, Limerick
Proposed development
The existing rear domestic garage, the concrete front yard, and the widening of the existing entrance as constructed. Planning Permission is also sought for the conversion of the existing side garage to a habitable room, together with the construction of side and rear extensions to the existing dwelling house, including a new roof canopy to the front elevation and all associated site works
- Applicant
- Not published
- Authority
- Limerick City and County Council
- Decision due
- Not available
Timeline
Application received
24 Nov 2025
Last day for public submissions (est.)
Tue 6 Jan 2026
Council asked for further information
26 Jan 2026
Decision due
Not available
Site location with nearby applications
Can't object to this one
The 5-week submission period has ended.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
demolition of existing single storey side and rear extensions and to construct a new two storey side extension, single storey rear extension and new site boundary. The proposed extension will accommodate a separate independent residential unit and will result in a sub division of the site and all associated site works
removal of existing temporary classroom and the construction of two permanent classrooms and all associated site works
the removal of the existing illuminated three-dimensional signage above the front entrance and permission to replace with surface-mounted flat signage, externally illuminated from above, together with all associated ancillary works and services
construction of a new wastewater pumping station consisting of: Foul Wet Well chamber containing submersible pumps, Inlet and screening chamber upstream of the new Wet Well, Foul Valve chamber downstream of the Wet Well, Vent Stack, Storm Return Pumps, Flow Meter chamber for foul rising main, Wet Kiosk and washdown area, Lifting mechanisms, Welfare facilities, incorporated with MCC kiosk, Site security provided with 2.4m palisade fencing, Emergency Storage Tank and associated pumping system, Motor Control Center (MCC) Container for control panel, Interconnecting pipework and ducting, Extended internal site access road, Hardstanding around tanks and chambers and All related site works and ancillary development
an attic conversion incorporating a dormer window and Velux roof windows together with all ancillary site works
removing the existing unauthorised signage to the exterior of the building and to provide new signage