Loch Lodge, Boycetown, Enfield
Proposed development
A single storey extension to side and rear of existing dwelling, new porch to front, together with modifications to existing elevations and internal plan layout and all associated site works
- Applicant
- Not published
- Authority
- Kildare County Council
- Decision due
- 18 Apr 2019
Timeline
Application received
22 Feb 2019
Decision due
18 Apr 2019
Decision: conditional
15 Apr 2019
Grant issued
28 May 2019
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
for the erection of a 24 metre high lattice telecommunications support structure on a 1.2 metre high raised foundation (providing an overall height of 25.2 metres) together with associated antennas and dishes and to remove the existing 15 metre lattice telecommunications structure with antennas (resulting in an overall height of 16.85 metres). The proposed development is all enclosed within an existing compound
for a detached, two storey dwelling and detached garage with associated ancillary works including modified entrance, boundary treatment, landscaping, on-site treatment system and percolation area. All associated site works
for the construction of a detached, two storey, dwelling and detached garage with associated ancillary works including modified entrance, boundary treatment, landscaping, on-site treatment system and percolation area. All associated site works
For 1) Retain the following: a) the partially constructed 2-story 15 bed staff accommodation; b) the demolition of outbuildings; c) wastewater treatment system; d) temporary portacabin office unit (for period of 5 yrs); e) construction delivery overflow area; f) perimeter site security fencing. 2) Permission is being sought to a) complete a partially constructed 15 bed staff accommodation; b) reconfigure the site entrance; c) add additional fencing; d)provide onsite parking; e) carry out all ancillary site works
1. Retain the following; a) The partially constructed 2 storey 15 bed staff accommodation; b) the demolition of outbuildings; c) wastewater treatment system; d) temporary portacabin office unit (for a period of 5 years); e) construction delivery overflow area; f) perimeter site security fencing; 2. Permission is being sought to; a) complete the partially constructed 15 bed staff accommodation b) reconfigure the site entrance; c) add additional fencing; d) provide onsite parking; e) carry out all ancillary site works
the construction of a single storey dwelling house, domestic garage, vehicular entrance, including wastewater treatment unit and percolation area, and all associated site works