Dunloe Upper, Beaufort, Co. Kerry
Proposed development
1. Demolish part of existing dwelling at the rear. 2 Build new extensions to the rear and front of existing house. 3 Construct a new roof.
- Applicant
- Not published
- Authority
- Kerry County Council
- Decision due
- 17 Jun 2026
Timeline
Application received
23 Mar 2026
Council asked for further information
13 May 2026
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
21 May 2026
Decision due
17 Jun 2026
Decision: conditional
17 Jun 2026
Grant issued
21 Jul 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
Planning permission is sought for development comprising: • The phased development of staff accommodation lodges in two connected three-storey blocks arranged around a central courtyard area, comprising: - Phase A development of 60 no. staff accommodation rooms and 6 no. common room areas; and - Optional Phase B development of a further 18 no. staff accommodation rooms in an extension to one of the blocks. • Roof-mounted photovoltaic panels and green roof systems on the proposed accommodation lodge buildings. • Construction of a single-storey gym building with attached bicycle and bin storage facilities. • Staff car parking facilities and associated internal vehicular and pedestrian connections to existing parking area, including provision for fire tender access. • Landscaping works including localised ground reprofiling, hard and soft landscaping works. • Lighting provision. • Localised connections to existing wastewater and water supply and provision of surface water drainage including soakaway area. • All associated site development works.
Retention Permission to retain existing temporary works already carried out, consisting of the removal of a timber fence, removal of flagpoles, erection of a mobile site cabin and installation of a localised hardcore surface and Permission to construct a temporary site entrance on the L4040 Road in the same location consisting of the removal of existing Heras fencing, laying of a new temporary tarmacadam surface locally, and erection of new temporary site hoarding and entrance gate. The combined retained existing works and proposed new works will constitute a temporary entrance to facilitate development previously granted permission under a separate application (Ref. 2460988). The hotel entrance configuration will be reinstated to its original condition upon completion of the permitted hotel development
Retention permission to (A) retain extensions and elevational changes to existing house as constructed, (B) full planning permission to construct a new wastewater treatment unit and sand polishing filter along with all associated site works, (C) retain garage as constructed for use as domestic garage and (D) retention permission to retain all developments within revised site boundaries
to retain (a) the rear extensions to the as-built dwelling house, (b) detached domestic sheds A, B, & C, (c) and all existing on-site development within revised site boundaries (previously granted under planning Reg. no. 300/72 and planning permission to decommission existing effluent treatment system and install a new septic tank and ANUA puraflow module system overlaying a soil polishing filter
Permission to construct 1 nr farm machinery shed, all in accordance with plans and particulars submitted
Retain existing shed as constructed