MANOR WEST AND CAMP, TRALEE, CO. KERRY
Proposed development
THE DEMOLITION OF AN EXISTING SHED AND THE CONSTRUCTION OF A NEW ACCESS ROAD AND BRIDGE FROM THE EXISTING N70/N22 ROUNDABOUT AT CAMP, TRALEE TO CONNECT WITH EXISTING MANOR RETAIL PARK INTERNAL ROAD AND ALL ASSOCIATED ANCILLARY DEVELOPMENT. A NATURA IMPACT STATEMENT (NIS) WAS SUBMITTED TO THE PLANNING AUTHORITY WITH THE APPLICATION
- Applicant
- Not published
- Authority
- Kerry County Council
- Decision due
- 17 Aug 2021
- Residential units
- 1
- Floor area
- 1 m²
Timeline
Application received
19 Oct 2020
Council asked for further information
10 Dec 2020
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
4 Jun 2021
Decision due
17 Aug 2021
Decision: conditional
17 Aug 2021
Appeal decided: refused (311256-21)
3 Mar 2022
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
Retention Permission to A) Retain the existing dwelling and shed within revised Site Boundaries and Permission to B) Demolish existing shed on site, C) Construct a new dwelling house, D) Create a new vehicular entrance to serve the new dwelling, and E) All associated site works
Retention Permission to retain Granny Flat as constructed and Planning Permission to complete Granny Flat ancillary to the existing house at 9 Maple Court, Tralee, Co. Kerry
CHANGE OF USE FROM WAREHOUSING/STORAGE/DISTRIBUTION AS GRANTED UNDER PLANNING REF NO. 23/599 TO FOOD MANUFACTURING, STORAGE AND DISTRIBUTION
Planning permission to refurbish and extend our existing dwelling house by erecting a new single-story pitched roof extension to the east side, with two Velux roof windows to the rear of the new roof and one Velux to the rear of the existing roof. The development will include all associated ancillary site works, including the demolition of the front boundary wall to the side patio area
Planning Permission to construct a new ESB substation and associated building at Manor Retail & Leisure Park, Tralee, Co. Kerry.
A) Change of use of existing first floor restaurant/retail/offices (837.1sq.m), and storage/services on the ground floor (35sq.m) including an internal access stair to use as a gym facility. Internal alterations to the existing layout to accommodate the proposed change of use, B) external alterations to the elevations to include provisions for a new 24/7 access entrance at ground floor level, internal stair alterations and new access lift to first floor level, C) new signage to the front elevations and all ancillary site development works and site services.