GORTNASKEHA COMMONS, BALLYBUNION
Proposed development
(A) RETAIN EXTENSIVE SITE WORKS WHICH INCLUDE DEMOLITION OF 80% OF AN EXISTING STONE COTTAGE/OUTHOUSE, NEW FOUNDATIONS, NEW RISING WALLS AND NEW SUBFLOORS (B) PERMISSION TO DEMOLISH THE REMAINING COTTAGE STRUCTURE AND DECOMMISSIONING OF AN EXISTING SEPTIC TANK (C)PLANNING PERMISSION TO COMPLETE THE DWELLING HOUSE INCORPORATING THE ORIGINAL STONE COTTAGE AS CLADDING TO PORTIONS OF THE NEW DWELLING WITH THE INSTALLATION OF A NEW WASTE WATER TREATMENT UNIT AND POLISHING FILTER WITH ALL ASSOCIATED SITE WORKS
- Applicant
- Not published
- Authority
- Kerry County Council
- Decision due
- 16 Nov 2017
- Residential units
- 1
- Floor area
- 1 m²
Timeline
Application received
24 Jul 2017
Council asked for further information
14 Sept 2017
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
20 Oct 2017
Decision due
16 Nov 2017
Decision: conditional
15 Nov 2017
Grant issued
19 Dec 2017
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
for Planning Permission for, to construct a dwelling house and detached domestic shed and to install new septic tank and percolation area and all associated site works, all the above at Lahesheragh North Lisselton Co.Kerry.
Retention permission (1) to retain the demolition of part of existing dwelling,(2) retention permission to retain construction of dwelling up to and including ground floor level as built and all associated works (3)and Permission for completion of dwelling as Pl Reg 24/77 and all associated site works
Full planning permission to A), demolish existing rear extension, B) construct new side & rear extensions onto the existing dwelling house, C) elevation changes & internal alterations to existing dwelling house, D) decommission existing septic tank & install a new mechanical treatment system & soil polishing filter and all associated site works
(1) CHANGE OF USE OF EXISTING GROUND FLOOR SHOP TO RESIDENTIAL USE, (2) TO EXTEND AND RAISE EXISTING ROOF, (3) TO CONSTRUCT NEW REAR GROUND FLOOR EXTENSION, (3) TO INSERT NEW WINDOWS TO NORTH AND SOUTHERN GABLES OF EXISTING DWELLING, (5) PLANNING PERMISSION FOR NEW MECHANICAL WASTEWATER TREATMENT SYSTEM AND RAISED SAND POLISHING FILTER AND ALL ASSOCIATED SITE WORKS
RETAIN DETACHED SINGLE STOREY STNADALONE HOME OFFICE/GYM STRUCTURE TO FRONT AS CONSTRUCTED AND PLANNING PERMISSION FOR (A) DEMOLITION OF CHIMNEY STACKS, SINGLE STOREY EXTENSIONS TO SIDE (SOUTH) AND DETACHED DOMESTIC GARAGE TO FRONT, (B) CONSTRUCTION OF PART SINGLE STOREY, PART TWO STOREY EXTENSION TO SIDE (SOUTH) AND DETACHED SINGLE STOREY REPLACEMENT GARAGE TO FRONT, (C) ALTERATIONS TO FENESTRATION/OPES AT GROUND AND FIRST FLOOR LEVELS TO ALL FOUR ELEVATIONS, (D) ADDITION OF 4 NO. ROOF LIGHTS TO SIDE (NORTH) ROOF PLANE AND (E) DECOMMISSIONING OF THE EXISTING SEPTIC TANK AND UPGRADE TO A NEW PRIVATE ON-SITE WASTEWATER TREATMENT SYSTEM AND (F) ALL ANCILLARY SITE WORKS
ERECT A BUNGALOW WITH A MECHANICAL AERATION UNIT AND FILTRATION AREA. ALSO TO ERECT A DOMESTIC GARAGE/UTILITY STORE AND ALL ASSOCIATED SITE WORKS ON HIS SITE