Kilmore, Brinny, Co. Cork
Proposed development
The development will consist of: 1. An extension to the existing sand & gravel pit with extraction area of c. 9.8 hectares worked on a phased basis. 2. Continued use of development granted planning permission under P. Ref. 24/6269 comprising the existing processing plant and related water management system; the existing concrete plant; ancillary buildings (site office (63 sq.m), 3 no. welfare portacabins (32 sq.m, 23.5 sq.m & 22.0 sqm), 4 no. storage buildings / containers (15 sq.m, 10 sq.m, 6 sq.m & 5 sq.m), 2 no. garages (76 sqm & 76 sq.m), ESB Substation (26 sq.m)); covered vehicle storage (220 sq.m); site access and all related ancillary facilities (wheelwash, fuel storage tank, weighbridge); and recycling of c. 15,000 tonnes of concrete per year for use in concrete production. 3. Phased and final restoration to agricultural use. All within an application area of c. 18.3 hectares. Permission is sought for fifteen years plus two years for final restoration (total duration 17 years). An Environmental Impact Assessment Report (EIAR) will be submitted to the Planning Authority with the application.
- Applicant
- Not published
- Authority
- Cork County Council
- Decision due
- 24 Aug 2026
Timeline
Application received
13 Mar 2026
Decision due
24 Aug 2026
Decision: grant with conditions
24 Aug 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
Permission for the construction of a 449.8msq (including 77.1msq Mezzanine) purpose-built operational infrastructure facility, supporting essential civil engineering and utility services, including secure storage areas for plant, machinery, and other construction materials and tools required soley in connection with the applicant's civil engineering and utility contracting business, a revised vehicular entrance and gate, internal circulation areas, parking and operational hard standing, 10m x 7m external storage area, storing Clause 804 and pipe grit for emergency use, associated surface water drainage infrastructure, waste water treatment system to serve wc and all other ancillary site development works.
Permission for the construction of 3690msq purpose-built operational infrastructure, supporting essential civil engineering and utility services, including secure storage areas for plant, machinery, aggregates and other construction materials and tools required solely in connection with the applicant' s civil engineering and utility contracting business, a revised vehicular entrance, internal circulation areas, service yards and operational hard standing, associated surface water drainage infrastructure and all other ancillary site development works
Permission to: a) Demolish existing porch to the front (south-western) elevation of the existing dwelling house, b) Demolish existing storage building to the side (south-eastern) elevation of the existing dwelling, c) Alter the front (south-western) elevation of the existing dwelling house including removing door and replacing this with a window of similar size and also extending the size of an existing window which will be changed to include a new door, d) Construction of two new dormer windows on the front (south-western) elevation of the existing dwelling house, e) Construction of a new pitched roof over the existing rear single storey area (north-eastern) of the existing dwelling house including raising the ridge height of this area, f) Construction of a new extension to the side (south-eastern) elevation of the existing dwelling house, g) Construction of a new vehicular entrance.
Permission for retention and continued use of existing processing plant and related water management system, the existing concrete plant, ancillary buildings (site office 63 sq.m), 3 no. welfare portacabins (32 sq.m, 23.5s q.m & 22.0 sq.m), 4 no. storage buildings/containers (15 sq.m, 10 sq.m, 6 sq.m & 5 sq.m), 2 no. garages (76 sq.m & 76 sq.m), ESB Substation (26 sq.m), covered vehicle storage (220 sq.m), site access and all related ancillary facilities (wheelwash, fuel storage tank, weighbridge etc), permitted under Pl.Reg.No. S/02/1023), all for a duration of 10 years. 2) Permission for proposed development comprising removal of existing disused fuel storage tanks, recycling of c.15,000 tonnes of concrete for use in concrete production, importation of 25,000 tonnes of sand & gravel for processing, importation of c. up to 20,000 tonnes of soil and stone per year (under Article 27) for phased site restoration with a revised phasing plan and completion of restoration of the overall site to agricultural use. Permission is sought for eight years plus two years final restoration, total of 10 years. All within an application area of c.21.4 hectares.
1) Permission for retention and continued use of the existing processing plant and related water management system, the existing concrete plant and ancillary buildings, site access and all related ancillary works/facilities (wheel wash, bunded fuel storage with hydrocarbon interceptor, weighbridge, etc.) permitted under Pl.Reg.No. S/02/1023), all for a duration of 10 years. 2) Permission for proposed development comprising recycling of c. 15,000 tonnes of concrete for use in concrete production, importation of 25,000 tonnes of sand & gravel for processing, importation of c. up to 20,000 tonnes of soil and stone per year (under Article 27) for phased site restoration with a revised phasing plan, and completion of restoration of the overall site to agricultural use. Permission is sought for eight years plus two years for final restoration, total of 10 years. All within an application area of c. 21.4 hectares.
The proposed development will comprise an extension (extraction area c. 10.8 hectares) of the existing sand & gravel pit (Pl.Ref.No. S/02/1023); completion of extraction within the existing sand & gravel pit; continuance of use of the existing processing plant and related water management system; continuance of use of the existing concrete plant and ancillary buildings; continuance of use of existing access; importation of c. 180,000 tonnes of inert soil and stone for site restoration; recycling of c. 15,000 tonnes of concrete for use in concrete production; phased restoration of the overall site to agricultural use; and all related ancillary works/facilities within an application area of c. 35.7 hectares. Permission is sought for eight years plus two years for final restoration (total duration of ten years). The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR).