ObjectRight
Back to search
26/0624Grantedpermission

Kilmore, Brinny, Co. Cork

Not open for objections: The council has already decided this application.

Proposed development

The development will consist of: 1. An extension to the existing sand & gravel pit with extraction area of c. 9.8 hectares worked on a phased basis. 2. Continued use of development granted planning permission under P. Ref. 24/6269 comprising the existing processing plant and related water management system; the existing concrete plant; ancillary buildings (site office (63 sq.m), 3 no. welfare portacabins (32 sq.m, 23.5 sq.m & 22.0 sqm), 4 no. storage buildings / containers (15 sq.m, 10 sq.m, 6 sq.m & 5 sq.m), 2 no. garages (76 sqm & 76 sq.m), ESB Substation (26 sq.m)); covered vehicle storage (220 sq.m); site access and all related ancillary facilities (wheelwash, fuel storage tank, weighbridge); and recycling of c. 15,000 tonnes of concrete per year for use in concrete production. 3. Phased and final restoration to agricultural use. All within an application area of c. 18.3 hectares. Permission is sought for fifteen years plus two years for final restoration (total duration 17 years). An Environmental Impact Assessment Report (EIAR) will be submitted to the Planning Authority with the application.

Applicant
Not published
Authority
Cork County Council
Decision due
24 Aug 2026
Official file, drawings & documents on the council portal

Timeline

  1. Application received

    13 Mar 2026

  2. Decision due

    24 Aug 2026

  3. Decision: grant with conditions

    24 Aug 2026

Loading map…

Site location with nearby applications

Can't object to this one

The council has already decided this application.

See applications open for objections →

Keep an eye on this area

We'll email you when new applications are lodged nearby.

Planning history within 750 m

26/2222Invalid

Permission for the construction of a 449.8msq (including 77.1msq Mezzanine) purpose-built operational infrastructure facility, supporting essential civil engineering and utility services, including secure storage areas for plant, machinery, and other construction materials and tools required soley in connection with the applicant's civil engineering and utility contracting business, a revised vehicular entrance and gate, internal circulation areas, parking and operational hard standing, 10m x 7m external storage area, storing Clause 804 and pipe grit for emergency use, associated surface water drainage infrastructure, waste water treatment system to serve wc and all other ancillary site development works.

Kilmore, Brinny, Innishannon, Co. Cork. Cork County Council Received 26 Aug 2026
26/1969Invalid

Permission for the construction of 3690msq purpose-built operational infrastructure, supporting essential civil engineering and utility services, including secure storage areas for plant, machinery, aggregates and other construction materials and tools required solely in connection with the applicant' s civil engineering and utility contracting business, a revised vehicular entrance, internal circulation areas, service yards and operational hard standing, associated surface water drainage infrastructure and all other ancillary site development works

Brinny, Innishannon, Co.Cork Cork County Council Received 23 Jul 2026
25/6238Granted

Permission to: a) Demolish existing porch to the front (south-western) elevation of the existing dwelling house, b) Demolish existing storage building to the side (south-eastern) elevation of the existing dwelling, c) Alter the front (south-western) elevation of the existing dwelling house including removing door and replacing this with a window of similar size and also extending the size of an existing window which will be changed to include a new door, d) Construction of two new dormer windows on the front (south-western) elevation of the existing dwelling house, e) Construction of a new pitched roof over the existing rear single storey area (north-eastern) of the existing dwelling house including raising the ridge height of this area, f) Construction of a new extension to the side (south-eastern) elevation of the existing dwelling house, g) Construction of a new vehicular entrance.

Brinny, Innishannon, Co. Cork. Cork County Council Received 21 Oct 2025
24/6269Granted

Permission for retention and continued use of existing processing plant and related water management system, the existing concrete plant, ancillary buildings (site office 63 sq.m), 3 no. welfare portacabins (32 sq.m, 23.5s q.m & 22.0 sq.m), 4 no. storage buildings/containers (15 sq.m, 10 sq.m, 6 sq.m & 5 sq.m), 2 no. garages (76 sq.m & 76 sq.m), ESB Substation (26 sq.m), covered vehicle storage (220 sq.m), site access and all related ancillary facilities (wheelwash, fuel storage tank, weighbridge etc), permitted under Pl.Reg.No. S/02/1023), all for a duration of 10 years. 2) Permission for proposed development comprising removal of existing disused fuel storage tanks, recycling of c.15,000 tonnes of concrete for use in concrete production, importation of 25,000 tonnes of sand & gravel for processing, importation of c. up to 20,000 tonnes of soil and stone per year (under Article 27) for phased site restoration with a revised phasing plan and completion of restoration of the overall site to agricultural use. Permission is sought for eight years plus two years final restoration, total of 10 years. All within an application area of c.21.4 hectares.

Kilmore Brinny Co Cork Cork County Council Received 29 Nov 2024
24/5882Awaiting decision

1) Permission for retention and continued use of the existing processing plant and related water management system, the existing concrete plant and ancillary buildings, site access and all related ancillary works/facilities (wheel wash, bunded fuel storage with hydrocarbon interceptor, weighbridge, etc.) permitted under Pl.Reg.No. S/02/1023), all for a duration of 10 years. 2) Permission for proposed development comprising recycling of c. 15,000 tonnes of concrete for use in concrete production, importation of 25,000 tonnes of sand & gravel for processing, importation of c. up to 20,000 tonnes of soil and stone per year (under Article 27) for phased site restoration with a revised phasing plan, and completion of restoration of the overall site to agricultural use. Permission is sought for eight years plus two years for final restoration, total of 10 years. All within an application area of c. 21.4 hectares.

Kilmore Brinny Co Cork Cork County Council Received 7 Oct 2024
24/4712Awaiting decision

The proposed development will comprise an extension (extraction area c. 10.8 hectares) of the existing sand & gravel pit (Pl.Ref.No. S/02/1023); completion of extraction within the existing sand & gravel pit; continuance of use of the existing processing plant and related water management system; continuance of use of the existing concrete plant and ancillary buildings; continuance of use of existing access; importation of c. 180,000 tonnes of inert soil and stone for site restoration; recycling of c. 15,000 tonnes of concrete for use in concrete production; phased restoration of the overall site to agricultural use; and all related ancillary works/facilities within an application area of c. 35.7 hectares. Permission is sought for eight years plus two years for final restoration (total duration of ten years). The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR).

Kilmore Brinny Co Cork Cork County Council Received 25 Apr 2024