Tullig, Leap, Co. Cork
Proposed development
Construction of a proposed new detached dwelling house with car port, detached garage, provision of septic tank with percoliation area and all associated site works
- Applicant
- Not published
- Authority
- Cork County Council
- Decision due
- 1 Dec 2025
Timeline
Application received
6 Oct 2025
Decision due
1 Dec 2025
Decision: grant permission
26 Nov 2025
Grant issued
9 Jan 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
Permission for renovation and extension of existing ruined dwelling house, installation of wastewater treatment system and alla ssociated site development works
Permission to demolish existing old cattle house, permission to construct (a) a milking parlour, (b) dairy, (c) plant room, (d) office, (e) roofed cattle holding yard, (f) slatted soiled water tank, (g) roofed cattle handling yard, (h) extension to existing cow house, (i) two no. slatted slurry tanks, (j) feed storage bin, (k) rainwater harvesting tank and carry out all associated site works
Construct a dwellinghouse and garage and to install a waste water treatment system and carry out all associated works
a) 12 No. warehouses for the maturation of whiskey, (3 No. blocks of 3 warehouses, 1 No. double warehouse block and 1 No. single warehouse), each Warehouse has a total ground floor area of circa 1,530m² with an overall total floor area of 18,360m² and an overall height of 11.45m. The Warehouses will be single storey in nature. b) Single storey Service Building with a ground floor area of circa 124.5m² (c) New 9m wide x 3m high planted embankment to perimeter of bonded Warehouse site (d) New 3m high security fence and security access gates to perimeter of bounded Warehouse site (e) New 540 cum fire-fighting tank (f) New sprinkler fire-fighting tank (g) New fire water retention tank (h) Demolition of existing unhabitable farmhouse and outbuildings (i) New internal road network and associated staff parking areas (j) Associated site excavations and recontouring works (k) Ancillary boundary treatments and access road enhancement (l) All associated site works
a) 8 no. Twin Bay Warehouses for the maturation of whiskey, each Warehouse has a total ground floor area of circa 1,530 m2 with an overall total floor area of 24,480 m2 and an overall height of 11.45m. The warehouses will be single storey in nature. b) Single storey Service Building with a ground floor area of circa 124.5m2. c) New 9m wide x 3m high planted embankment to perimeter of bonded Warehouse site. d) New 3m high security fence and security access gates to perimeter of bounded Warehouse site. e) New 540 cum fire-fighting tank. f) New sprinkler fire-fighting tank, g) New fire water retention tank. h) Demolition of existing unhabitable farmhouse and outbuildings. i) New internal road network and associated staff parking areas. j) Associated site excavations and recontouriing works. k) Ancillary boundary treatments and access road enhancement, l) All associated site works
The development consists of the demolition of an existing dwelling house and for the construction of a new detached dwelling, waste water treatment system and all associated site works at Tullig, Leap, Co.Cork.