Keel Boherbue Mallow Co. Cork
Proposed development
Permission to construct a new dwelling house and domestic garage served by mechanical aeration unit & soil polishing filter.
- Applicant
- Not published
- Authority
- Cork County Council
- Decision due
- 9 Feb 2026
Timeline
Application received
28 Aug 2025
Decision due
9 Feb 2026
Decision: conditional permission
9 Feb 2026
Grant issued
20 Mar 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
Permission to Retain existing dwelling house, mechanical aeration unit and sand polishing filter and all associated site works within revised site boundaries
Retention Planning Permission to retain existing dwelling house, mechanical aeration unit and sand polishing filter and all associated site works within revised site boundaries.
Permission for alterations and extension to existing dwelling consisting of the following: 1) Renovations to existing dwelling and the construction of a single storey extension to the side of same dwelling. 2) To install a new secondary wastewater treatment system and tertiary filter to serve existing dwelling. 3) The construction of a new site entrance to serve existing dwelling and all associated site works and services.
Erect a 24m high lattice telecommunications support structure together with associated telecommunications equipment all enclosed in security fencing and to extend the existing access track.