Garraunawarrig Upper Newmarket Co. Cork
Proposed development
Permission for the Retention of the following (a) Front porch to dwelling (b) Detached domestic garage to front of dwelling (c) Single storey extension to side of dwelling (d) Prefabricated timber framed domestic store to rear of dwelling & Permission to upgrade existing vehicular entrance and ancillary works.
- Applicant
- Not published
- Authority
- Cork County Council
- Decision due
- 6 Nov 2025
Timeline
Application received
13 Mar 2025
Decision due
6 Nov 2025
Decision: conditional permission
5 Nov 2025
Grant issued
17 Dec 2025
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
Permission for retention of dwelling including conservatory, front porch and attached garage and amended site boundaries as existing. Permission for decommissioning and removal of septic tank and installation of waste water treatment unit to dwelling and associated works
Retention of dwelling including conservatory, front porch and attached garage, and permission for de-commissioning and removal of septic tank and installation of wastewater treatment unit to dwelling and associated works.
Permission for retention of dwelling, including conservatory, front porch and attached garage, septic tank and percolation area servicing the dwelling and associated works.
Upgrade to the existing waste water treatment plant (WWTP) with proposed plant including balance tank, anoxic, anaerobic and aeration tanks, proposed clarifier tank, Dissolved Air Flotation (DAF) plant, underground effluent pumping station, culverts, control room, filters and concrete plinths. The proposed development will include the demolition of the existing 11 meter bio-tower at the Newmarket Co-Operative Creameries Ltd facility in Newmarket town, Co Cork, within the townlands of Garrannawarrig Upper, Park, Garrannawarrig Lower and Liscongill. Installation of an underground pumped pipeline to convey treated water from the facility to a discharge point on the River Dalua, 4 kilometers to the south east of the facility, utilizing the R576 road corridor, including all necessary pipeline connection, drainage and vent infrastructures. Intensification of use of the existing facility through an increase in the duration of the weekly and annual milk processing period at the Newmarket Creamery resulting in an increase in milk processing up to a maximum of 80 million gallons per annum. These changes will be subject to an amendment by EPA, of the existing site Industrial Emissions Directive Licence. An Environmental Impact Statement and Natura Impact Statement accompany this planning application. The proposed development includes work to Allen’s Bridge, a recorded monument under the National Monuments Act and is located within the zone of potential for the historic town of Newmarket which has a Recorded Monument designation.
Upgrade to the existing waste water treatment plant (WWTP) with proposed plant including balance tank, anoxic, anaerobic and aeration tanks, proposed clarifier tank, Dissolved Air Flotation (DAF) plant, underground effluent pumping station, culverts, control room, filters and concrete plinths. The proposed development will include the demolition of the existing 11 meter bio-tower at the Newmarket Co-Operative Creameries Ltd facility in Newmarket town, Co Cork, within the townlands of Scarteen Lower, Garrannawarrig Upper, Park, Garrannawarrig Lower and Liscongill. Installation of an underground pumped pipeline to convey treated water from the facility to a discharge point on the River Dalua, 4 kilometers to the south east of the facility, utilizing the R576 road corridor, including all necessary pipeline connection, drainage and vent infrastructures. Intensification of use of the existing facility through an increase in the duration of the weekly and annual milk processing period at the Newmarket creamery resulting in an increase in milk processing up to a maximum of 80 million gallons per annum. These changes will be subject to an amendment by EPA, of the existing site Industrial Emissions Directive Licence. An Environmental Impact Statement and Natura Impact Statement accompany this planning application. The proposed development includes work to Allen’s Bridge, a recorded monument under the National Monuments Act and is located within the zone of potential for the historic town of Newmarket which has a Recorded Monument designation.
Upgrade to the existing waste water treatment plant (WWTP) with proposed plant including balance tank, anoxic, anaerobic and aeration tanks, proposed clarifier tank, Dissolved Air Flotation (DAF) plant, underground effluent pumping station, culverts, control room, filters and concrete plinths. The proposed development will include the demolition of the existing 11 meter bio-tower. Installation of an underground pumped pipeline to convey treated water from the facility to a discharge point on the River Dalua, 4 kilometers to the south east of the facility, utilizing the R576 road corridor, including all necessary pipeline connection, drainage and vent infrastructures. Intensification of use of the existing facility through an increase in the duration of the weekly and annual milk processing period at the Newmarket creamery resulting in an increase in milk processing up to a maximum of 80 million gallons per annum. The proposed development includes work to Allen’s Bridge.