Ballygarvan Quarry Killanully Ballgarvan Co.Cork
Proposed development
Permission for a Hydrogenated Vegetable Oil (HVO) generator and associated works within the existing permitted quarry (planning ref QR10, an Board Pleanála ref;04.QC.2012) comprising 1 no. HVO generator, 1 no. fuel storage tank (internally bunded) on a concrete slab ( approx. 39 sqm), palisade fencing surrounding generator and fuel storage tank, all within an application area of 0.024 hectares at the existing Ballygarvan Quarry.
- Applicant
- Not published
- Authority
- Cork County Council
- Decision due
- 22 Apr 2025
Timeline
Application received
27 Feb 2025
Decision due
22 Apr 2025
Decision: conditional permission
18 Apr 2025
Grant issued
27 May 2025
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
We, Roadstone Ltd., intend to apply to Cork County Council for a 30-year planning permission for the development of a vertical extension at this site, the existing Ballygarvan Quarry in the townlands of Killanully, Kilnahone and Ballygarvan, Co. Cork. The proposed development consists of: • Development of a vertical extension to the existing quarry comprising extraction, processing and washing of limestone and soil from an area measuring approximately 5.4ha and will allow for the extraction of approximately 1,303,798m3 of material; • Construction of an aggregate washing plant (including filter press, water supply tank, and water management network); • Construction of a quarantine area comprising a concrete foundation slab and inspection shed (gross floor area of 625m2); • Infilling and restoration of the existing and future quarry void over an area of approximately 14.7ha. It is proposed to fill the void with soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be notified to the EPA as an Article 27 by-product. There will be a phased restoration of the quarry void working from the base of the void vertically building up soil and stone. Following completion of the infilling works, natural colonisation of plant species will occur from the seedbank within the redistributed soil; • Continued use of existing operational infrastructure including weighbridge, office, wheel-wash facility, maintenance workshop, lime shed, water storage tanks, refuelling area and plant and machinery storage area; • Continued use of existing site access via the existing entrance off the R613; • All associated site development works. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development.
We, Roadstone Ltd., intend to apply to Cork County Council for a 30-year planning permission for the development of a vertical extension at this site, the existing Ballygarvan Quarry in the townlands of Killanully, Kilnahone and Ballygarvan, Co. Cork. The proposed development consists of: • Development of a vertical extension to the existing quarry comprising extraction, processing and washing of limestone and soil from an area measuring approximately 5.4ha and will allow for the extraction of approximately 1,303,798m3 of material; • Construction of an aggregate washing plant (including filter press, water supply tank, and water management network); • Construction of a quarantine area comprising a concrete foundation slab and inspection shed (gross floor area of 625m2); • Infilling and restoration of the existing and future quarry void over an area of approximately 14.7ha. It is proposed to fill the void with soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be notified to the EPA as an Article 27 by-product. There will be a phased restoration of the quarry void working from the base of the void vertically building up soil and stone. Following completion of the infilling works, natural colonisation of plant species will occur from the seedbank within the redistributed soil; • Continued use of existing operational infrastructure including weighbridge, office, wheel-wash facility, maintenance workshop, lime shed, water storage tanks, refuelling area and plant and machinery storage area; • Continued use of existing site access via the existing entrance off the R613; • All associated site development works. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development.
We, Roadstone Ltd., intend to apply for a 30-year planning permission for a vertical extension at this site, the existing Ballygarvan Quarry in the townlands of Killanully, Kilnahone and Ballygarvan, Co. Cork. The development consists of: Provision of an extension to the existing quarry comprising extraction, processing and washing of limestone and soil from an area measuring approximately 5.4ha and will allow for the extraction of approximately 1,303,798m3 of material; Construction of an aggregate washing plant (including filter press, water supply tank, and water management network); Construction of a quarantine area comprising a concrete foundation slab and inspection shed (gross floor area of 625m2); Provision of infilling and restoration of an existing and future quarry void over an area of approximately 14.7ha. It is proposed to fill the void with soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be notified to the EPA as an Article 27 by-product. There will be a phased restoration of the quarry void working from the base of the void vertically building up soil and stone. Following completion of the infilling works, natural colonisation of plant species will occur from the seedbank within the redistributed soil; Continued use of existing operational infrastructure including weighbridge and office, wheel-wash facility, maintenance workshop, lime shed and plant, water storage tanks, refuelling area and plant and machinery storage area; Continued use of existing site access arrangements via the existing entrance off the R613; All associated site development works. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development.
Permission for the continuation of use of existing construction and demolition (C&D) waste recovery facility at Killanully, Ballygarvan, co.Cork (previously permitted under Cork County Council Planning Ref. 16/05993). Recovery activities principally comprise crushing of construction and demolition waste materials using mobile plant and stockpiling of materials on existing hard standing area on site of 1.9 hectares with in an existing quarry. The application also includes provision for a waste inspection shed (35m2) and a new wheel wash at the site. The recovery facility will continue to share other existing site infrastructure including a portacabin office and weighbridge
Extend rear of existing single storey dwelling and to construct first floor extension, alterations to elevations of existing dwelling provision of access ramps, upgrade existing waste water treatment plant and all associated site works.
To extend rear of existing single storey dwelling and to construct first floor extension, upgrade existing wastewater treatment plant and all associated site works.