Eli Lilly pharmaceutical manufacturing complex, Ballythomas West, Ballythomas East, Horsehill More (North), Ballyvrin Lower, Dunderrow Kinsale, Co. Cork.
Proposed development
A 10-year permission to construct a phased extension of the existing on-site Landscaped Earthen Berm previously permitted under Pl.Reg.No. 16/6558, 18/6137 and 21/6812 at the east of the overall campus. The proposed Landscaped Earthen Berm extension will cover an area of approximately 14,400m2, within a development area of 2.32 hectares, and formed with naturalised contours with slope grade of approximately 33% to a maximum height of approximately 8m above established ground level. All associated site development works including modification to the adjacent site storm water management features and site landscaping. The proposed development is located on a site that operates under an existing Industrial Emissions (IE) Licence (No. P0009-05) under Part IV of the Environmental Protection Agency Act 1992 (as amended for the Protection of the Environment Act, 2003). The proposed development is on a site which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 (S.I 209 of 2015) applies.
- Applicant
- Not published
- Authority
- Cork County Council
- Decision due
- 19 Feb 2025
Timeline
Application received
17 Dec 2024
Decision due
19 Feb 2025
Decision: conditional
18 Feb 2025
Grant issued
1 Apr 2025
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
The construction of a temporary 360-space carpark, together with a construction storage area, widening of the existing vehicular access from 6.5m to 10m, associated egress/ pedestrian access points, lighting and fencing. The carpark will operate for a period of between two and five years. The proposed development is covered by an Industrial Emissions Directive Licence No. P0009-05. As the proposed development refers to modification to an establishment to which the Major Accident Directive applies, information as specified in the third schedule of the Major Accident Regulations will be submitted with the application.
Planning permission to construct a new dwelling house
The construction of a temporary 360-space carpark, together with a construction storage area, associated egress/ pedestrian access points, lighting and fencing. The carpark will operate for a period of between two and five years. The proposed development is covered by an Industrial Emissions Directive Licence No. P0009-05. As the proposed development refers to modification to an establishment to which the Major Accident Directive applies, information as specified in the third schedule of the Major Accident Regulations will be submitted with the application.
Permission to construct a new dwelling house.
Planning permission to construct a new dwelling house.
Planning permission to construct a new dwelling house