2560578Refusedpermission

Slievenalicka, Illaunbaun Drumbaun, and Lackamore

Not open for objections: The council has already decided this application.

Proposed development

For the development at this site in the townlands of Slievenalicka, Illaunbaun, Drumbaun and Lackamore (although no infrastructure will be sited within Lackamore townland), Co. Clare. The development will consist of: • Construction of 1 wind turbine with a maximum overall blade tip height of 150m. • Construction of associated turbine foundation, crane pad hardstand and assembly area. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbine to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction and operation of the turbine. • Two borrow pits. • One peat repository area for peat and spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent and Temporary tree felling to accommodate the construction and operation of the turbine. • Signages. • All associated site development works. This application is seeking a 10-year planning permission, together with a 35-year operational life for the wind turbine from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) Yes. The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) and Screening for Appropriate Assessment have been prepared in respect of the planning application and will be submitted to the Planning Authority with the application

Applicant
Not published
Authority
Clare County Council
Decision due
17 Dec 2025
Official file, drawings & documents on the council portal

Timeline

  1. Application received

    19 Sept 2025

  2. Decision due

    17 Dec 2025

  3. Decision: refused

    15 Dec 2025

Loading map…

Site location with nearby applications

Can't object to this one

The council has already decided this application.

See applications open for objections →

Keep an eye on this area

We'll email you when new applications are lodged nearby.

Similar applications refused nearby

Since 2019 the council has refused these applications for the same kind of development (solar or wind energy) within 300 m, and they weren't overturned on appeal. They're useful planning history for your letter, and we'll suggest them when you object.

Planning history within 750 m

2660207Under appeal

for the development of the Slievenalicka wind turbine in the townlands of Tooreen, Slievenalicka, Drumbaun & Lackamore (although no infrastructure will be sited within Lackamore townland), County Clare. The development will consist of: • Construction of 1 wind turbine with a maximum overall blade tip height of 150m. • Construction of associated turbine foundations, crane pad hardstand and assembly areas. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbines to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction & operation of the wind farm. • Two borrow pits. • One peat repository area for peat & spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent & Temporary tree felling to accommodate the construction & operation. • Signages and • All associated site development works. This application is seeking 10-year planning permission, along with a 35-year operational life for the wind farm from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413). The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) has been prepared in respect of the planning application and will be submitted to the Planning Authority with the application

Tooreen, Slievenalicka, Drumbaun & Lackamore Clare County Council Received 31 Mar 2026
2560520Under appeal

for the development of Illaunbaun Wind Farm in the townlands of Tooreen, Slievenalicka, Illaunbaun, Drumbaun & Lackamore (although no infrastructure will be sited within Lackamore townland), County Clare. The development will consist of: • Construction of 5 wind turbines with a maximum overall blade tip height of 150 m. • Construction of associated turbine foundations, crane pad hardstand and assembly areas. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbines to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction & operation of the wind farm. • Two borrow pits. • Three peat repository areas for peat & spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent & Temporary tree felling to accommodate the construction & operation. • Signages and • All associated site development works. This application is seeking 10-year planning permission, along with a 35-year operational life for the wind farm from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) Yes x No The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) & Screening for Appropriate Assessment have been prepared in respect of the planning application and will be submitted to the planning authority with the application.

Tooreen, Slievenalicka Illaunbaun, Drumbaun and Lackamore Co Clare Clare County Council Received 27 Aug 2025