The Bawn, Killeshandra, Co. Cavan
Proposed development
To (a) construct single storey extension to side of existing dwelling (b) construct two storey extension incorporating a balcony to rear of existing dwelling together with alterations to plans/elevations, (c) change of use of existing lower ground floor space from garage & utility to habitable space (d) install waste water treatment system & percolation area previously approved under planning reference 2560018 and associated site works
This description looks cut short in the national planning register. Read the full description on the council's file
- Applicant
- Not published
- Authority
- Cavan County Council
- Decision due
- 8 Jan 2026
- Residential units
- 1
- Floor area
- 67 m²
Timeline
Application received
23 Sept 2025
Council asked for further information
14 Nov 2025
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
3 Dec 2025
Decision due
8 Jan 2026
Decision: conditional
23 Dec 2025
Grant issued
9 Feb 2026
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
for as-built single storey split level dwelling over garage and utility room (which differs in terms of orientation and position on site from Approved Plans, Reg. Ref. No. 645629) and associated site works. Planning Permission is sought for new rear site boundary
to replace existing 20m high telecoms wooden structure with a 24 metre high lattice communication structure, carrying communication dishes and antennae; along with all ancillary equipment including ground development works within an existing 2.4 metre high fenced compound
for a fully serviced, single storey duel level bungalow style dwelling, new sewage treatment & percolation area, asphalt driveway, entrance gate and all associated ancillary site works
for the demolition of the existing derelict feedmill production facility. The proposed works include for the demolition of the existing seven storey building and infilling of clean material on site. Works include all associated site development works