18244Grantedoutline permission

Slieve Rushen House, Gortawee or Scotchtown, Ballyconnell

Not open for objections: The council has already decided this application.

Proposed development

For development consisting of alterations, extension and change of use to Slieve Rushen House to form a Heritage and Ecological Visitor Centre, including toilet facilities, café, information display etc and meeting rooms and 1 no. self catering apartment with associated improvements and upgrade to the existing vehicular access and provision of new car-parking, picnic area and play-park and connection to the public sewer

Applicant
Not published
Authority
Cavan County Council
Decision due
7 Aug 2018
Official file, drawings & documents on the council portal

Timeline

  1. Application received

    13 Jun 2018

  2. Decision due

    7 Aug 2018

  3. Decision: conditional

    1 Aug 2018

  4. Grant issued

    10 Sept 2018

Loading map…

Site location with nearby applications

Can't object to this one

The council has already decided this application.

See applications open for objections →

Keep an eye on this area

We'll email you when new applications are lodged nearby.

Planning history within 750 m

2660165Granted

for: the surfacing of the existing hardstanding gravel areas to the north and west of the existing distribution facility, the provision of a designated parking area for HGVs and a staff car park in these areas together with all associated ancillary site works

Gortawee or Scotchtown & Rakeelan, Ballyconnell, Co. Cavan Cavan County Council Received 9 Apr 2026
2560506Granted

- RED III - for a solar energy development comprising ground mounted solar photovoltaic (PV) panels, mounted on steel support structures, underground cabling, temporary construction compound, erection of Transformer station (11kV), laying of a permeable gravel access track, widening of existing site (field) entrance, relocation of the existing ESB overhead line, erection of CCTV poles and cameras, erection of an entrance gate, artificial berm, landscaping and biodiversity measures all associated ancillary development works, for the purpose of generation renewable energy electricity. Planning Permission is sought for 35-year operation of the solar farm following which the site will be decommissioned, all development removed and the Site restored to agricultural lands

Lands to the South of Mannok Cement Works Entrance, In the Townlands of Gortawee or Scotchtown and Rakeelan, Ballyconnell County Cavan Cavan County Council Received 27 Aug 2025
2560481Awaiting decision

for a solar energy development comprising ground mounted solar photovoltaic (PV) panels, mounted on steel support structures, underground cabling, temporary construction compound, erection of Transformer station (11kV), laying of a permeable gravel access track, widening of existing site (field) entrance, relocation of the existing ESB overhead line, erection of CCTV poles and cameras, erection of an entrance gate, artificial berm, landscaping and biodiversity measures all associated ancillary development works, for the purpose of generation renewable energy electricity. Planning Permission is sought for 35-year operation of the solar farm following which the site will be decommissioned, all development removed and the Site restored to agricultural lands

Lands to the South of Mannok Cement Works Entrance, In the Townlands of Gortawee or Scotchtown and Rakeelan, Ballyconnell County Cavan Cavan County Council Received 15 Aug 2025
2460045Awaiting decision

for thirty-year permission for a grid system services facility located at Gortawee, Mucklagh, Ballyconnell, County Cavan, over an area of c.3.46 hectares. The proposed works shall consist of the installation and operation of energy storage units, including 1no. customer switchgear containers and compound, which will be connected to the national grid via the adjacent Gortawee 110kV substation infrastructure, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary infrastructure

Gortawee, Mucklagh, Ballyconnell Carlow County Council Received 29 Feb 2024
2460072Granted

to apply for thirty-year permission for a grid system services facility located at Gortawee, Mucklagh, Ballyconnell, County Cavan, over an area of c.3.46 hectares. The proposed works shall consist of the installation and operation of energy storage units, including 1no. customer switchgear containers and compound, which will be connected to the national grid via the adjacent Gortawee 110kV substation infrastructure, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary infrastructure on land

Gortawee, Mucklagh, Ballyconnell Cavan County Council Received 29 Feb 2024
2360327Withdrawn

for thirty-year permission for a grid system services facility located at Gortawee, Mucklagh, Ballyconnell, County Cavan, over an area of c.3.46 hectares. The proposed works shall consist of the installation and operation of energy storage units, including 1no. customer switchgear containers and compound, which will be connected to the national grid via the adjacent Gortawee 110kV substation infrastructure, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary infrastructure on land

Gortawee, Mucklagh, Ballyconnell Cavan County Council Received 20 Dec 2023