Dublin Rd., Carlow, Carlow
Proposed development
Retention of a mobile home to be used as a domestic unit for a period not more than 2 years during the construction phase of an extension to my existing dwelling and all associated site works
- Applicant
- Not published
- Authority
- Carlow County Council
- Decision due
- 20 Oct 2025
- Residential units
- 1
- Floor area
- 39 m²
Timeline
Application received
26 Aug 2025
Decision due
20 Oct 2025
Decision: conditional
13 Oct 2025
Grant issued
14 Nov 2025
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
A) Construction of a new first floor mezzanine of 58.2 m² within the existing Empower Fitness gym premises. B) Provision of a new internal staircase connecting the ground floor to the mezzanine level. C) Internal alterations including removal of walls, and all associated site works and services. D) Change of opening hours: Monday to Friday from 6 am – 9:30 pm to 6 am – 10 pm; Saturday from 9 am – 6 pm to 8 am – 6 pm; and Sunday from 9 am – 3 pm to 8 am – 5 pm
A) Construction of a new first floor mezzanine of 58.2 m² within the existing Empower Fitness gym premises. B) Provision of a new internal staircase connecting the ground floor to the mezzanine level. C) Internal alterations including removal of walls, and all associated site works and services. D) Change of opening hours: Monday to Friday from 6 am – 9:30 pm to 6 am – 10 pm; Saturday from 9 am – 6 pm to 8 am – 6 pm; and Sunday from 9 am – 3 pm to 8 am – 5 pm
A) Construction of a new first floor mezzanine of 58.2 m² within the existing Empower Fitness gym premises. B) Provision of a new internal staircase connecting the ground floor to the mezzanine level. C) Internal alterations including removal of walls, and all associated site works and services. D) Change of opening hours: Monday to Friday from 6 am – 9:30 pm to 6 am – 10 pm; Saturday from 9 am – 6 pm to 8 am – 6 pm; and Sunday from 9 am – 3 pm to 8 am – 5 pm
the installation of 3 no. electric vehicle (EV) chargers, ancillary equipment and all associated site development works
development at Four Lakes Retail Park, Dublin Road, Carlow, Ireland, R93 KV96. The development consists of the installation of 3 no. electric vehicle (EV) chargers, ancillary equipment and all associated site development works
a take-away coffee unit, a covered waiting area and all associated site works