Townlands of Ardenhue & Friarstown, Co. Carlow
Proposed development
For proposed works to include a solar and storage park on an area of approximately 68.8 hectares, comprising linear arrays of solar photovoltaic panels mounted on steel supported structures with associated cabling and ducting (including cable connection to the proposed onsite 110 kV tail fed substation), 50 inverter substations, a storage park (including 30 no. containers with battery cells, transformers and power conversion units), perimeter fencing, 8 no. palisade double security gates, 3 no. temporary construction compound/material storage areas, 6 no. steel storage containers, 17 no. turning bays, CCTV, a temporary construction stage wheel wash system and all associated ancillary development works. Elgin Energy Services Ltd. are applying for the proposed development to have planning permission that is effective for 10 years (and an operational period of 40 years). A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning Authority with the Planning Application.
- Applicant
- Not published
- Authority
- Carlow County Council
- Decision due
- 18 Apr 2023
Timeline
Application received
6 May 2022
Council asked for further information
29 Jun 2022
Further information received. If the council treats it as significant, a new submission period opens (check the council's file)
7 Sept 2022
Decision due
18 Apr 2023
Decision: conditional
18 Apr 2023
Grant issued
19 May 2023
Site location with nearby applications
Can't object to this one
The council has already decided this application.
See applications open for objections →Keep an eye on this area
We'll email you when new applications are lodged nearby.
Planning history within 750 m
to construct a part single storey, part two storey dwelling, detached single storey double garage, new entrance off existing laneway, bored well, waste water treatment system, percolation area and all associated site works
for proposed works to include a solar and storate park on a an area of approximately 68.8 hectares, comprising linear arrays of solar photovoltaic panels mounted on steel supported sturctures with associated cabling and ducting (including cable connection to the proposed onsite 110 kV tail fed substation), 50 inverter substations, storage park (including 30 no. containers with battery cells, transformers and power conversion units), perimeter fencing, 8 no. palisade double security gates, 3 no. temporary construction compound/ material storage areas, 6 no. steel storage containers, 17 no. turning bays, CCTV, a temporary construction stage wheel wash system and all associated ancillary development works. Elgin Energy Services Ltd. are applying for the proposed development to have planning permission that is effective for 10 years (and an operational period of 40 years). A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the planning application.
Permission for a development to include a solar farm on an area of approximately 17.6 hectares, comprising photovoltaic panels on ground mounted frames, 1 no. onsite 38kV substation, 10 no. single storey inverter/transformer stations, security fencing, a palisade double security gate, 2 no. storage containers, CCTV, a temporary construction stage wheel wash system and all associated ancillary development works. Elgin Energy Services Ltd. are applying for the proposed solar farm to have planning permission that is effective for 10 years (an an operational period of 40 years). A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the planning application
Permission for a development to include a solar farm on an area of approximately 17.6 hectares, comprising photovoltaic panels on ground mounted frames, 1 no. onsite 38kV substation, 10. no single storey inverter/transformer stations, security fencing, a palisade double security gate, 2 no. storage containers, CCTV, a temporary construction stage wheel wash system and all associated ancillary development works. Elgin Energy Services Ltd. are applying for the proposed solar farm to have planning permission that is effective for 10 years (and an operational period of 40 years). The planning application is accompanied with a Natura Impact Statement.
for proposed works which will include a solar farm on an area of approximately 27.0 hectares, comprising photovoltaic panels on ground mounted frames, 1 No., onsite 38kV substation, an energy storage system (4 No. units), 10 No. single storey inverter/transformer stations, security fencing, a palisade double security gate, 2 No. storage containers, CCTV, a temporary construction stage wheelwash system and all ancillary development works. Elgin Energy Services Ltd are applying for the proposed solar farm to have planning permission that is effective for 10 years (and an operational period of 35 years). The planning application incudes a Natura Impact Statement